19
INSTALLER
INSTALLER
12
ASSEMBLY OF THE INSULATION AND THE LINING
KOMBISOLAR 3S 750 - 1000
The assembly of the insulation and lining components must be
performed at the site of installation to facilitate passage through
any doors and/or entries to the room.
1
1
1
2
1
2
1
2
2
3
4
4
5
6
Proceed as follows:
− Assemble the insulating covers (1) around the body of
the heater, making sure that the engagement points on
the edges are positioned correctly. The edges are not re-
quired to be closed completely
− Place the front protection plate (2) correctly on the at-
tachments
− Put the washers on the attachments (3)
− Place the rear protection plate by closing the interlock-
ing flaps (4) without closing completely (leave one tooth
open)
− Apply the upper insulation (5) and the upper cover (6) (in
order to insert the cover, exert a light and homogeneous
pressure)
− Close the interlocking flaps (4) completely, which were
previously left with an open tooth
− Apply the technical data plate and serial number plate
If disassembling is required, proceed in reverse order.
9
Wear suitable personal protective equipment and use suit-
able safety devices.
0
Do not dispose of packaging material into the environment,
or leave it within the reach of children, since it can become
a potential hazard. Dispose of packaging material in com-
pliance with applicable legislation.
13
PLACE OF INSTALLATION
R
KOMBISOLAR 3S
combination storage cylinders can be in-
stalled in any room where there is no specific requirement for
an electrical protection rating higher than IP X0D.
≥ 0,4 m
≥ 0,6 m
≥ 0,3 m
≥ 0,4 m
9
Respect the minimum specified installation distances to
ensure correct installation and access for maintenance.
13.1
Installation in older systems and systems
requiring modernisation
When installing
R
KOMBISOLAR 3S
combination storage cylin-
ders in old systems or systems requiring modernisation, always
perform the following checks.
− Make sure that the system is fitted with safety and con-
trol devices in accordance with applicable legislation and
standards
− Make sure that the central heating circuit has been
flushed out to remove all sludge and lime scale, and has
been vented and seal tested
− Make sure that a suitable water treatment system is in-
stalled if the quality of the supply/recirculation water so
demands (refer to the reference values listed in the table
alongside).
REFERENCE VALUES
pH
6-8
Electrical conductivity
less than 200 μS/cm (25°C)
Chlorine ions
less than 50 ppm
Sulphuric acid ions
less than 50 ppm
Total iron
less than 0.3 ppm
Alkalinity M
less than 50 ppm
Total hardness
less than 35°F
Sulphur ions
none
Ammonia ions
none
Silicon ions
less than 30 ppm