Checklist for step-by-step installation procedure
The table below can be used as a checklist for the installation and commissioning
procedure for the HortiJet-Go!. The right column shows page references to the
relevant sections.
You can use the spaces in the left column to tick off each step as you complete it.
Completed No.
Step
Section to see for
this
Installation
1
Water installation
Connect the HortiJet to the two
branches from the main pipe.
Connect the fertilizer supply
hoses to the dosing channels.
"Connecting water
supply (hydronic
installation)" on
page 27.
2
Electrical installation
Connect the power supply,
network cable, main irrigation
pump and external meters and
valves.
"Connecting electrical
components" on
page 28.
3
Where applicable: connect the extra
dosing channels, sensors and/or I/O
modules.
"Installing other
components" on
page 28.
Commissioning
4
Use the latest software version for the
HortiMaX-Go!.
"Updating software"
on page 32.
5
Check the software configuration.
"Software
configuration" on
page 33.
6
Check the software settings.
"Software settings"
on page 36.
7
Calibrate the EC and pH sensors.
"Calibrating the
sensors" on page 37.
8
Pressurize the HortiJet
Open the manual valves on the
inlet and outlet for the HortiJet-
Go!.
Open the shut-off valves for the
PRV1 and the PSV.
Adjust the valves.
"Pressurizing the
HortiJet" on page 38.