How  do  I  know  whether  or  not  the
Nozzle Valve  is  open  on  a  loaded
projectile?

Why is the pressure in the Projectile lower
when I load it in the launcher than it was
when I filled it?

I  installed  a  Projectile  Cylinder  and
opened  the  Nozzle Valve,  and  I  hear  a
hissing from inside the Launcher Housing
– how do I stop this loss of air pressure?

The Valve Key will only depress fully when
the stem of the Valve Key is aligned with
the stem of the Nozzle Valve. Depress the
Valve  Key  in  the  vertical  and  horizontal
positions. Which ever position permits the
Key  to  fully  depress  will  represent  the
position of the Nozzle Valve. If horizontal
the Valve is Open. If vertical, the Valve is
closed. (fig 16a - d)

When  you  are  filling  the  projectile  with
air  it  will  get  warm. This  causes  the
pressure to rise and you will reach your
target pressure with the air in the bottle
at  a  temperature  higher  than  ambient.
Once air in the projectile has cooled down
the  air  will  contract  and  lower  the
pressure.

This problem is addressed by two steps:
1.  Fill  the  Projectile  Cylinder VERY

SLOWLY.

2. “Overfill” the Projectile by 200 psi./15 Bar

– to allow for the inevitable cooling of
the air after filling. See Filling, page 12)

In order of probability, you need to do the
following;

Tighten  Bleed  Screw  on  Launcher
Housing. (fig 14a)

Check to insure nylon insert is attached
to Bleed Screw. (fig 14b)

Check Nozzle Valve O-rings. (fig 23b)

If none of these steps solves the problem
contact  your  Rescue  Solutions
International distributor.

A

Q

A

Q

Safety Sheet

CAUTION:

The  use  of  any  other  compressed  gas  -  either  flammable  and/or  combustible,  may  result  in  a
spontaneous explosion causing severe injuries or death.

CAUTION:

If projectiles are subjected to extreme heat the pressure could rise sufficiently to rupture the
Pressure Relief Assy., and allow the air to escape, preventing use of the equipment. Refer to page
29 for instructions on removing and replacing the Pressure Relief Assy.

IMPORTANT NOTE:

The beveled surface of the neck of the nozzle is subject to wear at the moment of launching. In
normal conditions this part is suitable for 150 or more discharges. Carefully inspect this surface
for excessive wear after each use. If there is any question regarding suitability of this part for
continued use it must be removed from service and inspected by a qualified technician.

NOTE:

Inexpensive replacement cylinders are readily available from the manufacturer. 

DO NOT use

a visibly damaged cylinder!

NOTE:

DO NOT coil or loop the line, EVER! If you coil the line you may build in tension that will
cause snarls the next time you use it resulting in poor performance during deployment.

NOTE:

Some initial resistance may be experienced when trying to turn the Valve Key. However once
the Key begins to rotate it will turn easily. Be certain to rotate the Key a full 90 degrees.

Remember

If immersed in seawater, all lines and projectiles must be rinsed with fresh water and dried
thoroughly after use, and prior to being refilled or stored.

ATTENTION:

On firing, the unit exhibits a sound level in excess of 110 dB, which rapidly decays to background
levels within one minute. It is therefore recommended that ear defences systems are used during
operation of the product

The internal mechanism in this appliance is complex – and any maintenance or
repair other than that described in this manual should be performed by a
technician trained by the manufacturer in the repair of this equipment. Please
contact your Rescue Solutions International distributor for more information, call
1-800-709-5018 or e-mail at [email protected].

Содержание ResQmax

Страница 1: ...Operation Manual The Global Leader in intrinsically safe line throwing equipment TM the NEW Generation R E S CUESOLUTI O N S INC I N TERNATION A L...

Страница 2: ...any other aspect of this equipment call Rescue Solutions International Inc directly at 800 709 5018 or 760 727 8998 or by email at mail rescueinternational com Note See Disclaimer page 35 for an Impo...

Страница 3: ...in for service this record must be included Date of Purchase ResQmax Serial Projectile Serial Expiration Date Projectile Serial Expiration Date Projectile Serial Expiration Date Projectile Serial Expi...

Страница 4: ...tried to fire the launcher without disengaging the safety I then tried to disengage the safety but it seems jammed When you prepare to fire the launcher the mechanism is under pressure If you apply st...

Страница 5: ...injuries or death CAUTION If projectiles are subjected to extreme heat the pressure could rise sufficiently to rupture the Pressure Relief Assy and allow the air to escape preventing use of the equipm...

Страница 6: ...appliance fuled by compressed air specifically designed to deploy a line only or a grappling hook and line a grappling hook and ascending ladder to an otherwise inaccessible point in both land based...

Страница 7: ...ing actions Provide adequate and frequent training in the operation of this equipment in actual field conditions Implement and maintain a program for the regular review of the equipment to insure that...

Страница 8: ...Relief Assy 7 Place the O Ring around the threaded end of the Nozzle and screw the assembly back into the projectile cylinder Figure 23c Reinstalling the Nozzle Valve Plug Replacement of the Nozzle P...

Страница 9: ...erformance Important Note The beveled surface of the neck of the nozzle is subject to wear at the moment of launching In normal conditions this part is suitable for 150 or more discharges Carefully in...

Страница 10: ...ere is an O ring on the projectile nozzle which is re usable unless damaged A replacement O ring is included Do NOT use any sealant or tape on the thread of the nozzle Apply a small amount of Corrosio...

Страница 11: ...e care must be taken by the operator to avoid being struck by the Line and Hook during its downward descent Note Adequate training in all aspects of the use of this equipment is essential in order to...

Страница 12: ...t will be necessary to top it up using the procedure as described on page 11 This is also a good opportunity to have a practice launch Note If the Pressure Gauge on the Launcher does not show 0 pressu...

Страница 13: ...ok and install the projectile with Grappling Hook into the launcher The launcher is then ready for discharge following the steps outlined on page 26 for vertical deployment of the Grappling Hook Figur...

Страница 14: ...to the neck of the Projectile cylinder with velcro strap provided and return the Line to the blunt end of the projectile along the opposite side of the cylinder 6 Press the Safety Push Knob to insure...

Страница 15: ...the line container door closed V Groove Bridle Lines Quick connect Figure 17a Figure 17b Protecting the Cylinder or Projectile All practice deployments SHOULD BE INTOWATER The projectile is primarily...

Страница 16: ...on the line Note DO NOT coil or loop the line EVER If you coil the line you may build in tension that will cause snarls the next time you use it resulting in poor performance during deployment Figure...

Страница 17: ...it to service See Fig 14b Note The main line and bridle lines should be inspected after each use for fraying or damage before storing for later use If immersed in seawater during use all lines and pro...

Страница 18: ...projectile being inserted it is necessary to press the Safety Push Knob to release the safety internally prior to inserting another porjectile 19 Step 5 Step 4 Connecting the Launcher to the Line Cont...

Страница 19: ...projectile being inserted it is necessary to press the Safety Push Knob to release the safety internally prior to inserting another porjectile 19 Step 5 Step 4 Connecting the Launcher to the Line Cont...

Страница 20: ...it to service See Fig 14b Note The main line and bridle lines should be inspected after each use for fraying or damage before storing for later use If immersed in seawater during use all lines and pro...

Страница 21: ...on the line Note DO NOT coil or loop the line EVER If you coil the line you may build in tension that will cause snarls the next time you use it resulting in poor performance during deployment Figure...

Страница 22: ...the line container door closed V Groove Bridle Lines Quick connect Figure 17a Figure 17b Protecting the Cylinder or Projectile All practice deployments SHOULD BE INTOWATER The projectile is primarily...

Страница 23: ...to the neck of the Projectile cylinder with velcro strap provided and return the Line to the blunt end of the projectile along the opposite side of the cylinder 6 Press the Safety Push Knob to insure...

Страница 24: ...ok and install the projectile with Grappling Hook into the launcher The launcher is then ready for discharge following the steps outlined on page 26 for vertical deployment of the Grappling Hook Figur...

Страница 25: ...t will be necessary to top it up using the procedure as described on page 12 This is also a good opportunity to have a practice launch Note If the Pressure Gauge on the Launcher does not show 0 pressu...

Страница 26: ...e care must be taken by the operator to avoid being struck by the Line and Hook during its downward descent Note Adequate training in all aspects of the use of this equipment is essential in order to...

Страница 27: ...ere is an O ring on the projectile nozzle which is re usable unless damaged A replacement O ring is included Do NOT use any sealant or tape on the thread of the nozzle Apply a small amount of Corrosio...

Страница 28: ...erformance Important Note The beveled surface of the neck of the nozzle is subject to wear at the moment of launching In normal conditions this part is suitable for 150 or more discharges Carefully in...

Страница 29: ...Relief Assy 7 Place the O Ring around the threaded end of the Nozzle and screw the assembly back into the projectile cylinder Figure 23c Reinstalling the Nozzle Valve Plug Replacement of the Nozzle P...

Страница 30: ...ing actions Provide adequate and frequent training in the operation of this equipment in actual field conditions Implement and maintain a program for the regular review of the equipment to insure that...

Страница 31: ...appliance fuled by compressed air specifically designed to deploy a line only or a grappling hook and line a grappling hook and ascending ladder to an otherwise inaccessible point in both land based...

Страница 32: ...injuries or death CAUTION If projectiles are subjected to extreme heat the pressure could rise sufficiently to rupture the Pressure Relief Assy and allow the air to escape preventing use of the equipm...

Страница 33: ...tried to fire the launcher without disengaging the safety I then tried to disengage the safety but it seems jammed When you prepare to fire the launcher the mechanism is under pressure If you apply st...

Страница 34: ...in for service this record must be included Date of Purchase ResQmax Serial Projectile Serial Expiration Date Projectile Serial Expiration Date Projectile Serial Expiration Date Projectile Serial Expi...

Страница 35: ...any other aspect of this equipment call Rescue Solutions International Inc directly at 800 709 5018 or 760 727 8998 or by email at mail rescueinternational com Note See Disclaimer page 35 for an Impo...

Страница 36: ...w Body Cast In Inserts Fasteners Pressure Gauge Launcher Barrel Launcher Handle Line Container Cast In Inserts Fasteners Stock Body Cast In Inserts Fasteners Locking Slide Projectile Cylinder Projecti...

Отзывы: