VIONiC RTLC20/
FASTRACK
installation guide
5
DO NOT CUT
FASTRACK
carrier in
these areas
RTLC20/
FASTRACK
carrier installation
During handling or installation of the
FASTRACK
carrier suitable gloves should be worn to protect against injury from sharp edges.
2
Thoroughly clean and degrease the
substrate and allow to dry.
For the
FASTRACK
carrier location
a ledge, separate straight edge(s)
or dowels can be used.
Check alignment of ledge/separate
straight edge(s) with respect to axis
of motion
carrier installation drawing’ on page
4)
1
If required cut the
FASTRACK
carrier and scale to
length (separately) using guillotine (A-9589-0071)
after referring to installation drawing.
The guillotine should be held securely in place,
using a suitable vice or clamping method.
Feed
FASTRACK
carrier or scale through the
guillotine as shown, and place the guillotine press
block down onto the
FASTRACK
carrier or scale.
Ensure the block is in the correct orientation (as
shown). Whilst holding the block in place, in a
smooth motion, pull down the lever to cut through
the
FASTRACK
carrier or scale.
Before sticking the
FASTRACK
carrier to the substrate bend the
centre section upwards slightly
using a small pair of pliers.
3
4
IMPORTANT:
Wear suitable
protective gloves whilst
carrying out this procedure
to avoid risk of cuts.
5
Ledge
Side panels
Guillotine press
block
Remove backing liner and stick to substrate, locating
against ledge/separate straight edge(s) or dowels.
Ensure complete adhesion to the substrate by
applying firm finger pressure along the length
of the
FASTRACK
carrier from the centre
outwards towards each end using a lint-
free cloth if required.
NOTE:
Allow the
FASTRACK
carrier
a minimum of 20 minutes to
adhere before removing the
centre section.
Engage centre section removal tool and with consistent
forward pressure remove centre section.
If the ledge method or similar is used then the
appropriate side panel on the removal
tool (A-9589-0122) will need to be
removed as shown.