19. Plug the connectors from the flow switch wire har-
ness into the connectors just installed on the white
“spare” jumper. See Fig. 4.
20. Reinstall the sheet metal transformer cover.
21. Close front control panel and reinstall the four
screws (two at each end).
22. Reinstall front main panel door onto the heater.
23. Turn water on to the heater and check for leaks.
a. If leaks are found, repair immediately.
24. Turn on gas to the heater.
25. Turn on power to the heater.
26. Cycle the heater a few times to verify flow switch
operation.
www.raypak.com
Raypak, Inc., 2151 Eastman Avenue, Oxnard, CA 93030 (805) 278-5300 Fax (805) 278-5468
Litho in U.S.A.
FLOW SWITCH WIRES
CONNECTED TO “SPARE” JUMPER
Fig 4: “Spare” Jumper Connections
Fig 5: Completed Assembly