Installation:  

POWER SHOULD BE ISOLATED THROUGHOUT THE INSTALLATION PROCESS  

Step 1  

 

Secure metal box housing to 
wall or secure mounting 
position.  
 
The RAK system relies on 
being vertically mounted to 
allow the ventilation system to 
work properly.

 

Step 2  

 

Bring a separate 10A protected 
supply to each RAK case.  
 
Connect the Neutral and Earth 
to the buzz bars as shown.  
 
Bring the live to the front of the 
metalwork ready for connection 
to the circuit board. 
 
 

Step 3  

 

Bring a single Neutral and Earth 
from the buzz bars to the front 
of the metalwork. 
 
Prepare screws on either side 
of metalwork ready to hold the 
circuit board. They should be 
present and screwed loosely 
into the case.  