Installation - Rada 215-t3 c
1.
When unpacked, the inlet elbows are positioned to accept falling supplies. Should
the installation require rising or rear-fed supplies then the elbows will need
adjusting: loosen each elbow grubscrew (618 22) using 2.5 mm wrench key
provided, pull the elbow away from the valve body and refit in the desired position,
and re-tighten the grubscrew.
2.
Where rear-fed supplies are required, pipe concealing plates are provided which
recess into the tiling for a neater finish.
3.
Loosen backplate grub screws (618 22) using 2.5 mm wrench key provided and
pull off backplate (408 73).
4.
- For 15 mm compression pipework inlet or outlet connections: fit compression
nuts and olives supplied.
- For 1.2" BSP union inlet or outlet connections: fit flat-faced inserts supplied,
press in firmly (see
Figure 1
).
5.
Mount backplate securely to wall surface, with grub screws downwards, using
wall screws/plugs provided if appropriate.
6. Important:
Flush through the hot and cold supplies thoroughly before
connection to mixing valve
.
7.
Refit valve onto backplate and tighten grub screws.
8.
Connect inlet and outlet pipework, checking that the hot and cold supplies have
been piped to the correct inlets, and check all connections are watertight.
Refer to
COMMISSIONING
.
Figure 1 - Inlet/outlet Connectors Supplied
215-t3 c, 215-t3 bc (outlet only)
15 mm
542 10
408 71
Содержание 215-t3 Series
Страница 7: ...7 Rada 215 t3 dk Rada 222 t3 dk 65 153 65 179 108 82 33 86 37 29 29 108 65 65...
Страница 41: ...41 SPARE PARTS...
Страница 47: ...47 NOTES...
Страница 48: ...48 1057616 W2 A Kohler Mira Limited January 2006 CUSTOMER CARE...