C. Structural Requirements
C.1.1
RDB Graphic Unit
The RDB graphic unit is mounted on the curtain wall, centered between each pair of pinspotters.
The curtain wall will have to support a load of 35 Lbs – 16 Kg above each pair of pinspotters.
C.1.2
RDB Network Hub
The Network Hub is placed on the curtain wall,at the middle of the lanes. When more groups of
lanes are present, the hubs are each placed at the middle of groups, on the curtain wall.
C.1.3
OHRX - OHRGB - OHVGA Interface
The OH interfaces are located on the false ceiling, near the Overhead Monitors.
C.1.4 Overhead
Monitors
Overhead monitors are installed over the approach in the ball return area..
Static load weights for different configurations as follows:
•
Double 28” Monitors:
300 Lbs - 136 Kg
•
Triple 28” Monitors:
400 Lbs - 182 Kg
•
Double 34” Monitors:
450 Lbs - 204 Kg
•
Triple 34” Monitors:
675 Lbs - 306 Kg
•
Double 38” Monitors:
700 Lbs - 318 Kg
•
Double Plasma Screens: 300 Lbs - 136 Kg
See Tables C1-C8