MAINTENANCE   INSTRUCTIONS:

   

   

D

AILY

:

   

 

Clean    the    floor    in    the    DStacker,    removing    any    pallet    debris    or    dirt.            This    will    ensure    the   

pallets   rest   evenly   on   the   floor.   

   

   

   

W

EEKLY

:

   

 

Verify   that   the   PCM   is   functioning   properly.   

 

Once   the   pallet   stack   is   below   the   PCM’s   lower   extremity,   manually   push   the   left   PCM   into   its   

side   recess.      The   PCM   should   push   back   to   its   starting   position.      Next,   perform   test   on   right   

side.   

   

S

EMI   

A

NNUALLY

:

   

 

Test   each   of   the   four   (4)   latch   spring   mechanisms.   

 

Remove    the    pallet    stack    (as    per    Section    C)    from    the    DStacker    chamber.       Manually    push    one   

of   the   four   (4)   latches   inward.       The   latches   should   offer   some   resistance   and   will   return   to   
the   outward   position   once   released.      Perform   the   test   on   the   other   three   latches   individually.   

 

If    the    latch    does    not    return,    check    the    integrity    of    the    spring    mechanism    by    removing    the   

side   or   back   interior   metal   panel.   

Lubricate   the   two   (2)   counterweight   chains   with   a   30-­‐wt   lubricating   oil.      Access   the   chains   by   

removing   the   exterior   back   panel.   

 

Lubricate   the   two   rear   and   two   front   cam   follower   tracks   with   30-­‐wt   lubricating   oil.   

 

Check    hydraulic    oil    reservoir    level.       If    oil    is    below    MIN    level    indicator,    replenish    to    the    MAX   

level   indicator   mark.      

PLEASE   NOTE:      

Arctic   Supreme   32   Hi-­‐Performance   hydraulic   fluid   is   to   

be   used   in   the   DStacker   GS.

   

Содержание DStacker GS2

Страница 1: ...n 441 Industrial Road London Ontario Canada N5V 1T6 sales qtekdesign com 877 453 1880 Fax 519 451 3124 www qtekdesign com Operations Service Manual DStacker GS2 DStacker GS2 Part Serial Production Cod...

Страница 2: ...herwise the machine s functionality could be compromised 3 The site will require a minimum headroom clearance of 16 feet from the floor 4 The machine will require a minimum clearance around the unit a...

Страница 3: ...shipping brace 5 Install upper pallet magazine onto middle pallet magazine using forklift put 5 pallets into upper pallet magazine then lift upper pallet magazine and align onto middle pallet magazin...

Страница 4: ...hing the back wall before lowering them onto the pallets currently resting on the latches 5 Move the forklift back clear of the Dstacker and not allowing access to the pallets Hold down the priming sw...

Страница 5: ...ne is cleared operator must enable the PCM again by pressing inward on the PCM while releasing the Lock Out lanyard from the small black post Test the spring loaded PCM to verify that it is functionin...

Страница 6: ...chanisms Remove the pallet stack as per Section C from the DStacker chamber Manually push one of the four 4 latches inward The latches should offer some resistance and will return to the outward posit...

Страница 7: ...ad London Ontario L5V 1T6 Canada Service qtekdesign com www qtekdesign com M000001 QTEK DStacker GS2 INSTALLATION OPERATIONS MANUAL May 2015 Page 7 of 7 MACHINE ASSEMBLY photo 1 1 2 3 4 4 5 5 6 7 7 7...

Страница 8: ...ndon Ontario L5V 1T6 Canada Service qtekdesign com www qtekdesign com M000001 QTEK DStacker GS2 INSTALLATION OPERATIONS MANUAL May 2015 Page 8 of 8 OPERATING INSTRUCTIONS photo 1A 1A 1A 2A 2A 3A 4A 5A...

Страница 9: ...Industrial Road London Ontario L5V 1T6 Canada Service qtekdesign com www qtekdesign com M000001 QTEK DStacker GS2 INSTALLATION OPERATIONS MANUAL May 2015 Page 9 of 9 1C 2C 3C 1D 2D 3D 3D 3D 3D 3D 3D 3...

Отзывы: