Q4 CONTROLLER II Operation and Maintenance Manual
Q4 Controller II Operation Manual
- 21 -
Dec 02, 2021
85350-101-000 Rev A
6.10 Menu “I/O Setting”
For system installation testing, it is necessary to force relay, buzzer and strobe actions.
The Relay Testing forces an actuate vs. de-actuate action, not an energized vs. non-energized
action. Therefore, the user must be aware of those relays which have been defined as normally
energized or normally de-energized.
Settings
Description
Sensor & Modbus:
For Factory Testing only
Set Sensor port and Modbus port to be 19.2K Modbus RTU protocol with
no parity.
For QEL RS-485 Tester to quick test the RS-485 ports
Relay 1-4 Test:
Manually actuate / de-actuate Relay1 to Relay4
Buzzer & Strobe:
Manually actuate / de-actuate Buzzer1 to Buzzer3 and Strobe
6.11 Menu “Output Disable”
To disable the Q4 Controller functions for calibration. When operation is disabled, the relay,
strobe, etc., status will freeze in whatever state they are already in.
6.12 Menu “BACnet”
To support BACnet BAC-Box, the setting of “BACnet” must be Enabled. When it’s enabled, the
Modbus protocol is disabled automatically.
BAC-Box supports DHCP and static IP both IP address assignments. Each device must have a
unique IP address and unique BACnet ID# on a network. Your system administrator generally
provides the IP address and corresponding subnet mask and gateway if static IP address is
selected.
6.13 Q4C-II Modbus RTU protocol
Please contact QEL customer service for the Modbus protocol.