INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO XL-G11S.X / BFG
20
4 Electrical Connection
4.2 Electrical installation safety
Danger! Risk of fatal injury due to electric shock!
Be sure to maintain the time intervals as specified by
the inverter manufacturer between switching off the
inverter and beginning any further work.
Danger! Risk of fatal injury due to electric shock!
Never plug or unplug the cable when under load.
Modules must not carry any current.
1. Switch off the inverter.
OFF
EN
2. Switch off the DC circuit breaker.
3. Measure shutdown in DC String.
(no DC current flow).
4. Disconnect plugs by the use of appropriate
and qualified tools of the manufacturer.
5. When connecting the modules proceed in reverse
order.
Danger! Risk of fatal injury due to electric shock!
Electrical work may only be performed by qualified
and skilled personnel (see page 3).
Ensure correct polarity.