Initial Operation
English
Initial Operation
1. Test run
a.
Close the three drainage stop cocks and fill the tanks and replenishment con-
tainers with water. Open water inflow tap. Connect electrical socket and
switch the machine on. Water now flows into water tank. The circulation pump
activates, however the hosing of the machine must be ventilated.
b.
Ventilation of the replenishment pump:
Set temperature dial to position „Manual pumping“. Keep dial to this position
until no more air bubbles rise in the tanks.
c.
Ventilation of the circulation pump:
If air is in the circulation pump, a loud running noise can be heard. Switch the
machine off again. Open the stop cocks of the developer and fixer for five sec-
onds and then close them again. Then switch the machine on again. Repeat
this procedure until no more air bubbles are visible in the developer and fixer
baths and until the circulation pump runs quietly.
d.
Check all hose connections for leakage. Switch machine off and drain water
out.
2. Fill processor with chemicals
Prepare chemicals inside the replenishment containers according to manufacturers
instructions.
Fill up processor manually
By using a suitable container, pour chemicals into the respective tanks. First the fix-
er and then the developer. Caution: when filling, be sure that chemicals do no
splash from one bath into another. When fixer solution is mixed with developer so-
lution, the developer chemical is destroyed.
Snap each suction pipe into the respective cover of it’s replenishment container and
close it carefully. Place containers under processor.
Using replenishment pump
Filling of processor can also be done by use of the replenishment pump (this takes
much more time). The chemicals containers need to be filled manually with at least
1.0 litres of fresh chemicals, to ensure the pumps will not run dry. Snap each suction
pipe into the respective cover of it’s replenishment container and close it carefully.
Place containers under processor. Now set the temperature adjusting knob to po-
sition “Manual pumping”. Leave the knob in this position until the tanks have been
filled. After 20 minutes this function stops automatically - to restart a cycle, turn dial
to another position and return to „Manual pumping“. ›‹Limitation:
Limitation:
The
function may fill up tanks of developer and fixer to different levels. This may be due
to different causes. If this happens, then use a suitable container to fill up the tanks
completely.
Important!
Processor should not be run dry!
Upon commissioning and every refilling the pumps must be
vented.
Warning, hot surface!
Содержание FI-75 MAMMO
Страница 2: ...1 CP OPTI EU Declaration of Conformity EU Declaration of Conformity ...
Страница 35: ...34 CP OPTI Electric Diagrams ...
Страница 36: ...CP OPTI 35 Electric Diagrams English ...
Страница 37: ...36 CP OPTI Electric Diagrams ...