5
1.
Remove any trace of dirt and dust and ensure that the
surface is level, dry and clean.
2.
Cut the PROMASIL
®
-1000L boards to the right size.
Remove the sawdust and provide an opening in the
board for the smoke evacuation duct if necessary.
3.
Apply a layer of PROMAFOUR
®
-GLUE 1000 on the
entire surface of the boards and the edges by means
of a coarse-toothed glue spatula (3 mm). Depending
on the kind of surface, the quantity of glue needed
will be between 1.5 to 3 kg/m².
4.
Protect the floor and rear wall by providing an air
cavity. Also refer to points A and B under the section
‘Important recommendations’ on p.4 for a detailed
description.
5.
After a drying time of approximately 3 minutes, press
the PROMASIL
®
-1000L board firmly to the floor/rear
wall. Don’t forget to carefully press the sides of the
board also.
> Picture 5
6.
Then fix the board in each corner by means of screws
and an installation ring.
7.
Install your fireplace/stove following the instructions of
the manufacturer.
> Picture 7
Installation
5
7