Assembling procedures:

After you open the box, find and prepare parts as following: 

Handle with care the preassembled parts.

Boom use square pipes.
Front and back elements use round pipes

All measure are metrics in mm.

Be aware,

 put a little lubrification on stainless steel bolts because if screwed down fast, getting hot, 

could  stiff, (general rules valid for all stainless steel bolts).

Arrange square pipe, in line,  in a stepping down sequence  following labels and drawing.
Innestare i tubi l’uno dentro l’altro, ed imbullonarli tra loro con gli appositi bulloni. Le teste dei 
Insert the smaller square pipe end in the larger square pipe end, insert the bolt from bottom to top 
side and make sure that bolt head take place in the larger hole pressing on the inner square pipe. 

Boom 

The 

A

 label joints are on the front side, the 

B

 label joints are on the rear antenna side, both refered 

to mast-boom joint plate.

                 

On the antenna boom  are preinstalled already the wire elements insulators and RF wire line. After 
that the boom is completed, connect the line wires to next one, taking care to cross them.
RF wire line, back and front alluminum elements take place on the bottom boom face.
If you are assembling antenna on easels, preventing RF line wires damages, disconnect them in 
coincidence with easel, taking care to reconnect them back when assembling end.
 

If you have easy access to your tower rotating mast pipe , than install boom-mast plate on the 
antenna boom and install it on the tower, taking care to have RF lines and insulators facing down. 

Содержание LOG2010

Страница 1: ...m bottom to top side and make sure that bolt head take place in the larger hole pressing on the inner square pipe Boom The A label joints are on the front side the B label joints are on the rear antenna side both refered to mast boom joint plate On the antenna boom are preinstalled already the wire elements insulators and RF wire line After that the boom is completed connect the line wires to next...

Страница 2: ...ubrificate a bit the stainless steel bolts Screw down all nuts Make sure that all bolt heads are aligned on the same side Follow the same procedure for all tube connections When you have both half alluminum element ready than procede to assembly the center as in the picture below Make sure to have 8cm in between the line connection bolts Center view of back element dipole long one When back elemen...

Страница 3: ...th cases insert bolts from bottom side Before to screw down the self looking nuts check that both dipoles are correctly spaced from the nearest element Make sure that they are in square and screw down the bolts to have a solid cross Install the top trussed wire doing a knots on the back eye bolt pass trought the uphold pipe hole and go to the front side eye bolt pull to have the boom a little bit ...

Страница 4: ...re with the second one half loop When both wires are in place pull wires screwing the turnbuckle Make sure that both half loop are well balanced looking toward the boom it MUST be straight In the package there are 6 couple of steel wires elements they are galvanized steel protected with black UV resistent PVC with both ends eye terminated Unroll the wires elements select them by longer to shorter ...

Страница 5: ...Main antenna diagram Top view Back side view Side view Front ...

Страница 6: ...t be the same as the finished product the manufacturer reserves the right to make changes or modifications without prejudice to the final specifications Features Antenna perform in the range 13 30Mhz optimized in coincidence with Ham radio bands Performance may change due environimental conditions in which is installed Take care to install it at least 5 or more meters 15 or more ft over the ground...

Страница 7: ...icinity of exposed power lines or other sources of power at risk of lightning you may be killed or seriously injured Make sure anyone does not even come into contact with it accidental during use Install the antenna on properly dimensioned supports to hold the load even under stormy wind conditions The fall of all or part of it could hit people and or things with unrecoverable damages In case the ...

Страница 8: ... concerns our technical department is always ready to provide all the necessary help If you are satisfied with it tell the others otherwise tell to us Your opinion and your suggestions will help us to improve even more our products Best regards Annamaria Fiume IK7MWR Made in Italy WARNING Defend the environment Disposing components and materials The antenna consists mainly of aluminum in the event...

Отзывы: