Packaged and Split Rooftop Ventilator
Handling Concerns for Units with Packaged
DX
Units having packaged DX have a system that is
pressurized with refrigerant and if it is damaged, the
refrigerant could leak into the atmosphere or cause
bodily harm due to the extreme cold nature of expanding
refrigerant. Use protective equipment such as gloves
and safety glasses to minimize or prevent injury in case
of a system leak during installation.
Before Lifting - Field Power Access
Determine where high voltage and low voltage wiring is
to be brought into the cabinet. If wiring is to be brought
into the cabinet through the floor, see Alternate Supply
Entry Locations in this manual. If unit is to be installed on
a roof, cut access openings in the roof deck as needed.
Lifting
1. Before lifting, be sure that all shipping materials have
been removed from unit.
2. To assist in determining rigging requirements, weights
are provided in the Unit Weights & Dimensions
section of this manual.
3. Unit must be lifted by all lifting lugs provided at top of
unit.
4. Spreader bars must span the unit to prevent damage
to the cabinet by the lift cables.
5. Always test-lift the unit to check for proper balance
and rigging before hoisting to desired location.
6. Never lift unit by weatherhood.
7. Never lift units in windy conditions.
8. Preparation of curb and roof openings should be
completed prior to lifting unit to the roof.
9. Check to be sure that gasketing (supplied by others)
has been applied to the top of the curb prior to lifting
the unit and setting on the curb.
10. Do not use fork lifts for handling unit.
Use spreader bars to prevent damage to cabinet.
Additional Clearances for
Packaged DX Units
Packaged DX units require additional clearance
because they must have unrestricted air movement
around the condenser coil and condenser fans. Hot air
is being discharged from the condenser fans during
operation. Enough clearance must be provided to
avoid recirculation or coil starvation. When equipped
with condenser coils, the unit should never be placed
under an overhang or inside a building. A minimum of
48 inches above the condenser fans is acceptable, but
unobstructed is strongly recommended.
END VIEW OF MAKE-UP AIR UNIT
WITH PACKAGED DX
Minimum 48 inches clearance
Minimum 18 inches
clearance
Condenser Coil
Condenser Fans
End view of roof top unit with Packaged DX
.
© 2017 Mitsubishi Electric US, Inc.