6. Battery Operation
Now that you have installed the batteries you are almost ready to energise the system. First you should
check your installation to ensure the below:
• Check polarity of all battery connections to be correct.
• Check that there is no damage to cables.
• Check that all system breakers are in the off position.
• Check for adequate air flow as per you installation requirements.
• Check for local installation compliance if applicable.
Starting up the battery system should be done in conjunction with the PCE manufacturer’s
recommendations as well as this manual and any local or government safety requirements.
Each battery in the system is powered up separately by turning the double pole breaker to the ON position.
Once powered up, voltage will be present at the DC terminals and the Main Status LED light will glow blue.
6.1. Main Status LED
The Main LED Status indicator is used to understand the operation of the battery and the state of the BMS.
Status
Operational State
ON
Battery is ON and allowing charge and discharge.
OFF
Battery circuit breaker is in the OFF position.
OFF
Battery BMS is in low voltage protection mode - Charge will still be accepted, however discharge will not be
permitted until battery cell voltage is sufficient.
OFF
Battery is in high voltage protection mode - Charge will not be accepted, however discharge will continue
OFF
Battery is in temperature protection mode, the BMS has detected cell temperature outside of our operation
window of MAX 65°C. Charge or discharge will be disabled until cell temperature reduces.