26
Dual Gate Installations
Step 1
Make sure both gates are in the fully closed position.
Verify Block 2, DIP Switch #1,2,3 & 6 are in the ON position,
Step 2
Ensure power switch is in the ON position. Press the cycle
button on the circuit board and the gates will begin to open.
Stop the gates using the cycle button when the desired limit
for the primary gate has been reached.
Step 3
Press and hold the “SET LIMIT” button until you hear one
beep to acquire the open limit setting (fig. 29). The STATUS
light will turn on immediately upon pressing the SET LIMIT
button. The STATUS light will turn off and an audible beep
will verify the open limit is now set.
Step 4
Press cycle button on circuit board to return the gates to the
fully closed position.
Step 5
Again, press the cycle button on circuit board. The gates will
begin to open. The primary gate should stop at the open
limit position that was programmed in the previous steps.
The secondary gate will continue to open until you press the
cycle button.
Step 6 (setting secondary gate)
Set Block 2, DIP switch #6 to the ON position. Press and hold
the “SET LIMIT” button until you hear one beep to acquire
the open limit setting (fig. 29). The STATUS light will turn
on immediately upon pressing the SET LIMIT button. The
STATUS light will turn off and an audible beep will verify the
open limit is now set.
Step 7
Press the cycle button on circuit board to close both gates.
Then once again press the button to open the gates and
verify the open limits are set properly. If the gates did not
reach the desired open limits, proceed to step 8.
Step 8
CLEARING THE OPEN LIMIT SETTINGS:
a) Return the gates to the fully closed position.
b) Set Block 2, DIP switch #6 to the OFF position.
c) Press and hold the SET LIMIT button until two audible
beeps are heard. Two audible beeps will verify the open
limit setting is now cleared.
d) Set Block 2, DIP switch #6 to the ON position.
e) Press and hold the SET LIMIT button for until two audible
beeps are heard. Two audible beeps will verify the open
limit setting is now cleared.
Repeat steps 1 – 7 to program the gates “open limit setting”.
Figure 30
PUSH-TO-OPEN LIMIT SETTING
Содержание 502
Страница 22: ...22 WIRING OPERATOR ...
Страница 33: ...33 EXIT WAND HOOK UP DIAGRAM ...
Страница 34: ...34 PHOTO EYE HOOK UP DIAGRAM ...
Страница 35: ...35 PHOTO EYE HOOK UP DIAGRAM ...