INTRODUCTION
Install float valve and hose adapter
Attach the float valve to the cabinet as shown below.
Locate a knock-
out in the bottom of any of the four corner posts.
The garden
hose
adapter attaches to the brass inlet fitting on the float valve.
NOTE:
verify that the hose washers are correctly in place.
Water connection and float adjustment
Move cooler to desired location (this
must
be a level area for proper
operation of the cooler).
1.
Connect to water supply using a commercial grade of water hose
(not supplied with cooler, obtained separately) to the adapter on
the
float valve and turn water on. CAUTION: water inlet pressure
should
be limited to a maximum of 65 PSI to avoid rupturing the
water
hose. If pressure exceeds this value, an inline pressure
regulator
should be installed (obtainable from a local plumbing or
hardware
store).
2. Check that all connections are tight by visually inspecting hose, float
valve, etc. for leakage.
3. Set float valve for a water depth of 2-1/2". The float is adjusted by
lightly bending the float rod.
Your evaporative air cooler was thoroughly tested and inspected
before leaving the factory. This is your guide to economical, trouble
free comfort cooling over the years with reasonable care and regular
maintenance. Failure to follow these instructions may damage your
cooler, impair its operation and/or void the warranty
Read it carefully.
SET UP FOR ROLL-AROUND USE
• Open parts box & remove casters from parts bag. Assemble each
caster (Fig.1) per caster plate using supplied 1/4-20 nuts & carriage
bolts.
• Place casters w/ brakes on the front of the unit, and the casters
without the brakes should be mounted on the back of the cooler.
Use
16
of the 1/4-20 bolts from the parts bag to secure all 4 of the
casters to their respective caster plates. Apply brakes before lifting
cooler upright to complete assembly.
2 Master Blaster Use and Care Manual
PREPARATION FOR ASSEMBLY
Remove the pad frames by slightly lifting the pad frame from the
bottom, pull outwards until clear of cabinet bottom pan, then
downwards until frame clears cabinet top. Remove the following
items from the cooler:
1. Box containing swivel casters and attachment hardware.
2. Plastic bag containing small parts, float valve, garden hose adapter,
hose nut, hose washer, o-ring.
3. Bag with hose adapter for float valve (roll-around use)
Gather tools required to assemble & install unit
The following tools are required to assemble the unit:
7/16" box or open end wrench
3/8" box or open end wrench
6" crescent wrench
1/4" nut driver
Figure 1
Install Overflow Standpipe / Drain Line
Install overflow drain bushing in bottom of cooler as follows:
• Slide rubber washer over the brass drain
bushing.
• Push drain bushing through bottom of
cooler, assemble and tighten lock nut.
• Screw plastic overflow standpipe into the
drain bushing and tighten snugly (hand
tight) to prevent leakage.
• Where conditions allow for drainage,
connect a drain line (garden hose) to
drain bushing.
Motor and blower wheel check
Check motor mounting to be sure all screws and nuts are
tightened down properly. Rotate blower wheel by hand to see that
it moves freely without rubbing against housing.
Cooler checkout and first time start-up
Congratulations, once you re-install the pad frames, your roll-around
Master Blaster cooler will be complete and ready for use. Please
proceed to the Pre-startup inspection checklist on page 3 before starting
unit for the first time
.
CAUTION:
Never operate unit with pad frame(s)
and/or air outlet grille removed. This
will result in an overloaded condition