Set-up and Initial Commissioning
24
8
.06
Checking the start inhibitor function
O
Switch on the machine at the main switch and move the sewing head.
The error message "ERROR:
9
" must appear in the control panel.
O
If the message does not appear, check the start inhibitor setting as explained in
chapter
8.01.03 Assembling the start inhibitor
.
O
Right the sewing head and acknowledge the error message.
The machine is ready for operation again.
8
.04
Initial start-up
O
Remove the plug
1
of the oil reservoir
2
before the initial commissioning.
Danger of machine damage!
The plug
1
serves solely for
transit support and may not be
used during the sewing opera-
tions.
O
Inspect the machine, particularly the
electric cables, for any damage.
O
Clean the machine thoroughly, see also
chapter 12 Maintenance and Care
.
O
Arrange for technical staff to check
whether the machine's motor may be
operated at the existing mains voltage
and whether it is connected properly.
Never operate the machine if there are any differences.
The machine must only be connected to a grounded socket!
Fig. 8 - 06
1
2
8
.05
Switching the machine on / off
O
Switch the machine on (see
chapter 7.01 Main switch
).