Operation and maintenance manual for the Q-PER series boilers with feeders. The producer reserves the right to introduce technical modifications.

3.3.  Connection to chimney

1.  It is necessary to prepare stand-alone, tight chimney 

fl

ue, 

which will be used for 

fl

ue gas from the boiler.

2.  The 

fl

ue should be placed at least 1.5 m over the roof ridge 

to avoid the occurrence of backdraught. The intersection of 
the 

fl

ue should be appropriately selected for the boiler pow-

er and height of the chimney. Approximate calculations of 
chimney height and intersection can be carried out using 
a chimney intersection calculator available on the website 
www.pereko.pl Regardless of the results of the calculations 
the minimum intersection of masonry chimney should not 
be lower than 14 

×

 14 cm! The intersection of non-insulated 

steel chimneys should be bigger by 20% and the chimneys 
made from steel pipes should be about 15-20% higher than 
brick chimneys. 

3.  Check condition of the chimney (preferably by a chimney 

sweep)  before  connecting  the  boiler  to  the  chimney  and 
check whether the chimney if free from connections of the 
heating elements. 

4.  The boiler should be connected with chimney using a con-

nector. It is not recommended to use the connection at a 
straight angle because it will cause a loss in the chimney 
draught. Flue with chimney should be joined with a connec-
tor made of steel sheet of thickness 3 mm (to be purchased 
from the boiler producer). We put it on the outlet from the 

fl

ue, 

fi

x  on  the  chimney  and  seal  with  high-temperature 

silicone.  The  connector  should  be  directed  slightly  up-
wards from 5° to 20°. If boiler 

fl

ue will have a length over 

400 mm then it is recommended to insulate it with a thermal 
insulation.

NOTE! Boilers should be installed in compliance with the 
applicable  Regulation  of  the  Minister  of  Infrastructure 
(Journal of Laws of 2002 no. 75 item 690 and Journal of 
Laws of 2009 no. 56 item 461.) In addition, it is recom-
mended to use chimney liner resistant to corrosion: chem-
ical, pitting, intercrystalline and surface.

3.4.  Connection of central heating and domestic hot water system

3.4.1.  Open water heating installations

The Q-PER boiler is suitable for supplying open water central 
heating  systems  with  gravitational  or  forced  circulation.  The 
system  in  which  the  boiler  operates  must  meet  the  require-
ments  of  the  Polish  standard  PN-91/B-02413  Ogrzewnictwo 
i ciep

ł

ownictwo – Zabezpieczenie instalacji ogrzewania wod-

nego systemu otwartego – Wymagania / Heating and district 
heating Protection of open water heating installations – Speci

fi

-

cations/. The manufacturer reserves the right to introduce design 
modi

fi

cations.

Содержание Q-per 12

Страница 1: ...Operation and maintenance manual for the boilers with feeder Q Per...

Страница 2: ...rameters of the controller 13 4 5 Fuel refilling 14 4 6 Boiler stopping 14 4 7 Cleaning and maintenance 14 4 8 Emergency stopping of the boiler 15 5 BOILER OPERATION DISTURBANCES BEFORE CALLINGTHE SER...

Страница 3: ...ciency of the boiler ensure continuous access to the equipment avoid exceeding water temperature in boiler over 95 C maintain operating pressure not exceeding 2 bar NOTE Boiler installation in accorda...

Страница 4: ...n of pressurised equipment oper atingathighertemperatures Heatexchangerpanelsarewelded while the unit casing is reinforced with brackets Location of convection ducts allows cleaning using the upper do...

Страница 5: ...aust flue is an integral part of the boiler extracting exhaust gas towards the flue duct 2 3 9 Exhaust gas swirlers Exhaustgasswirlersareinstalledinconvectionductstoswirlthe exhaustgasstream whichincr...

Страница 6: ...gas at nominal power C 160 150 Temp of flue gas at minimum power C 70 80 Flue gas mass flow at nominal power g s 5 93 8 42 11 62 16 14 Flue gas mass flow at minimum power g s 1 83 3 29 4 54 8 81 Fuel...

Страница 7: ...tmaximum1movertheflooringornotlowerthan 200 cm2 for boilers with power up to 25 kW or 400 cm2 for boilers over 25 kW 2 separate air exhaust duct on the internal wall with cross sectionnotlowerthan140...

Страница 8: ...recommended to use the connection at a straight angle because it will cause a loss in the chimney draught Fluewithchimneyshouldbejoinedwithaconnec tor made of steel sheet of thickness 3 mm to be purc...

Страница 9: ...reserves the right to introduce technical modifications Equalizing tank Non return ball valve Non return valve Central heating pump Pump Boiler Heaters Storage type water heater for domestic hot water...

Страница 10: ...thecentralheatingdesignmustbefollowed Asam ple scheme of boiler connection with the central heating and domestic hot water systems in an open heating system with gravitational or forced water circuit...

Страница 11: ...t and is synonymous with loss of the warranty Thesystemcanberefilledwithwateronlywhentheboileris cold Firing up should be restarted after filling the system 3 6 3 Draining water from the system It is...

Страница 12: ...pera tures resulting in risk of burn injuries Do not stay on the side of the boiler during the opening of the doors and pay attention to flames Take care of cleanness in the boiler room ensure proper...

Страница 13: ...hecombustionprocess is taken by the controller see Controller instruction manual that maintains the set water temperature in the boiler with ref erence to the heat demand of the building 4 4 Approxima...

Страница 14: ...utton then scrape the heat to the ash pan using the hook supplied along with the boiler 4 7 Cleaning and maintenance Keepingtheboilercleanisnecessaryforitsreliableandfaultless operation Even a thin la...

Страница 15: ...rbancesinboileroperation and methods of dealing with them Symptom Cause Repair Smoking outwards insufficient chimney draught remove leaks in chimney flue or boiler doors insufficient chimney height li...

Страница 16: ...onths and 24 months for the components 6 Warranty for tightness of welding joints is not synonymous with warranty for tightness of the whole boiler and is appli cable in case of leaks only on welding...

Страница 17: ...ompatible with PN 91 B 02413 2 Incorrect connection in closed system acc to the Journal of Laws of 2009 no 56 item 461 3 Incorrect transport and storage of the boiler 4 Starting the boiler without suf...

Страница 18: ...18 Page Operation and maintenance manual for the Q PER series boilers with feeders The producer reserves the right to introduce technical modifications SERVICE ASSISTANCE Date Comments Signature...

Страница 19: ...is provided for 10 years 60 months for tightness of the heat exchanger and 24 months for the other components The beginning of the warranty period for the PEREKO boiler is the date of purchase confir...

Страница 20: ...ducer Envo sp z o o 27 200 Starachowice ul Radomska 76 POLAND www grupaenvo pl Technical support tel 48 41 274 53 53 fax 48 41 274 53 26 e mail serwis pereko pl mobile 48 602 315 512 604 953 459 660 7...

Отзывы: