P/N 840259
10
Rev. C 7-29-05
Sub-terrain Base & Deck Installation
1. Conduits set per PG2000 template.
3. Drive 3/8 in. rebar at an angle in the corners.
5.
For concrete deck mount, drill for two ½ in. lead shield anchors
provided and secure with lag screws and washers provided.
2. Cut sub-base flanges as needed.
4.
Backfill 1 to 4 in. below shoulder for mulch or concrete. Cut fiber
conduit below or at top of base.
ELECTRIC CONDUIT IN FRONT
AND EXTENDING 6 IN.
ABOVE SUB-BASE
Tools and Material Required:
√
Hammer
√
Side Cutters
√
Phillips Screwdriver
√
Hacksaw or PVC Cutters
√
Four 12 in. lengths of 3/8 in. Rebar or Rod
√
Drill with ½ in. Concrete Bit
√
Ratchet Driver w/4 in. Extension
√
½ in. Socket
ELECTRIC
CONDUIT
IN FRONT