Cut the water resistive barrier.

 Fold side flaps into the 

opening and staple to inside wall.

YOU WILL NEED TO SUPPLY:

TOOLS REQUIRED:

• Cedar or Impervious shims/spacers (12 to 20)
• 10d galvanized finish nails or #8 x 2 1/2" flat head corrosion-

resistant screws (4 to 6)

• Closed cell foam backer rod/sealant backer (20 to 35 ft.)
• Pella

®

 SmartFlash

 foil backed butyl window and door  

flashing tape or equivalent

• High quality exterior grade polyurethane or silicone sealant  

(1 tube per window)

• Great Stuff 

 Window and Door Insulating Foam Sealant 

by the Dow Chemical Company or equivalent low pressure 
polyurethane window and door foam - DO NOT use high 
pressure or latex foams

• Interior trim and/or jamb extensions (25 to 40 ft.)
• Knee braces (2)

• Tape measure
• Level
• Square
• Hammer
• Stapler
• Scissors or utility knife
• Sealant gun
• Drill with a #2 Phillips 

and a #3 square drive bit

• 3/16" wrench or socket
• 1/2" open end wrench

SEALANT

SEALANT

REMEMBER TO USE APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT.

A. 

Verify the opening is plumb and level.

Note: It is critical that the bottom is level.

1st cut

2nd

cut

3rd cut

Water Resistive Barrier

1C

B. 

Verify the window will fit the opening.

 Measure all four sides 

of the opening to make sure it is 3/4" larger than the window 

in both width and height. On larger openings measure the 

width and height in several places to ensure the header or studs 

are not bowed.

Note: 1-1/2" or more of solid wood blocking is required 

around the perimeter of the opening. Fix any problems with 

the rough opening before proceeding.

1E

1"

1/2"

1/2"

6"

1D

1   

ROUGH OPeNING PRePARATION

D. 

Apply sill flashing tape #1. 

Cut a piece of flashing tape 12" longer 

than the opening width. Apply at the bottom of the opening as 

shown (1D) so it overhangs 1" to the exterior.

Note: The tape is cut 12" longer than the width so that it will 

extend 6" up each side of the opening.

E. 

Tab the sill flashing tape and fold.

 Cut 1" wide tabs at each 

corner (1/2" from each side of corner) (1E). Fold tape to the 

exterior and press firmly to adhere it to the water resistive barrier.

Содержание 80AT0102

Страница 1: ...d with any other construction method Installation instructions for use with other construction methods multiple units or bow and bay windows may be obtained from Pella Corporation a local Pella retail...

Страница 2: ...T SEALANT REMEMBER TO USE APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT A Verify the opening is plumb and level Note It is critical that the bottom is level 1st cut 2nd cut 3rd cut Water Resistive Barrier...

Страница 3: ...fore the window is installed A Insert the window from the exterior of the building Place the seat of the window at the bottom of the opening and slide the top into position Center the window between t...

Страница 4: ...n at maximum torque Additional tensioning may be done with the nuts on the opposite end of the cable at the bottom of the bay bow unit 3 CABLE CLAMP INSTALLATION CROSS BRACING MOUNT NON ACCESSIBLE CAB...

Страница 5: ...A Install the cable clamps Drive the 12 x 3 1 4 square screws part way into the mounting surface using a 3 square drive bit B Secure the seat board and head board by using 10d finishing nails or 2 1 2...

Страница 6: ...with pliers to be able to insert into the space between the jamb boards and the rough opening and between the head and seat board and the rough opening Exterior 5A When applying siding brick veneer o...

Страница 7: ...bead of sealant on the leg of the head frame expander and install by tapping on using a block of wood with rounded edges and a hammer G Install the bottom frame expander by tapping on with a block of...

Страница 8: ...and unanticipated water infiltration deficiencies in building design construction and maintenance failure to install Pella products in accordance with Pella installation instructions or the use of Pel...

Страница 9: ...inerales NO utilice agentes abrasivos NO raye ni utilice herramientas que puedan da ar la superficie El uso de acabados solventes lavados de ladrillos o productos qu micos de limpieza inadecuados prov...

Страница 10: ...deados H Inserte la varilla de relleno en el espacio entre la cubierta de la jamba y el material de revestimiento exterior tan profundamente como pueda Aplique un reborde de sellador para exteriores d...

Страница 11: ...s marcos y la abertura y entre las tablas del cabecero y de asiento y la abertura sin terminar Exterior 5A Al aplicar revestimiento revestimiento de ladrillos u otros materiales de acabado exterior de...

Страница 12: ...una llave de 1 2 pulgada 1 27cm o un sujetador Esto evitar que el cable se tuerza ya que las tuercas hexagonales est n ajustadas con una llave B Asegure la tabla de asiento y la tabla del cabecero con...

Страница 13: ...ue los cuatro tornillos est n ajustados hasta su m xima torsi n Puede ejercerse presi n adicional ajustando las tuercas en el extremo opuesto del cable en la base de la ventana TABLA DEL CABECERO TABL...

Страница 14: ...el edificio Coloque el asiento de la ventana en la base de la abertura y luego deslice el borde superior para colocarlo en su lugar Centre la ventana entre los lados de la abertura a fin de que quede...

Страница 15: ...la abertura para asegurarse de que sean 3 4 de pulgada 19 mm m s grandes que la ventana tanto en ancho como en largo En aberturas de mayor tama o mida la anchura y la altura en varios lugares para as...

Страница 16: ...para otros m todos de construcci n unidades m ltiples o ventanas de mirador puede obtenerlas de Pella Corporation o de un vendedor local de productos Pella o visitando http www pella com Los dise os...

Отзывы: