Location Setup
2.4.1 Foundation
Provide a firm, level foundation, preferably made of concrete. The P-K MACH
®
boilers
must
be level
and upright to function properly.
There are s
ix 9/16” holes in the base which may be used for 3/8” or
1/2" anchor bolts. Once the boiler is installed on the foundation and furnished with anchor/lag bolts,
use a bubble level and adjust the anchor nuts until the appliance is secure and level.
Two wheels are provided for ease of movement. When the boiler is in position, the wheels can be
disconnected and will recess up into the boiler’s cabinet base. At a later date when the boiler is pulled
out for maintenance, these wheels can be re-connected.
NOTICE!
The appliance may be installed on a combustible floor; however, the appliance must
NEVER
be installed on carpeting.
NOTICE!
This appliance is certified for
INDOOR
use only!
QTY 3 (REAR)
9/16” Hole for
Anchor/Lag Bolts
QTY 3 (FRONT)
9/16” Hole for
Anchor/Lag Bolts
QTY 2
Rubber Wheels
The boiler must be level within 0.25° in order to function properly. Failure to heed this