Install controller into electronics rack.  Connect cables to rear making sure P1 and P2 are connected to correct
sockets. (P1 to J1 AND P2 to J2)  

Confirm controller voltage

 

and fuse are correct

, if not, convert to correct

voltage by following instructions in the controller manual Section 2.2.1.  Connect AC power cable to controller.

2.3  CONTROLLER INSTALLATION

Turn power on.  Wait for self-check to complete.  Hit mode button once to reach display/function mode.  Press
deploy button to Deploy.  Antenna will drive until:

ELEVATION

20.0º

(approx.)

AZIMUTH

 0.0º

POLARIZATION

                 0.0º

Press speed button to change speed to FAST

HAVE SOMEONE OUTSIDE AND ELEVATED SO ANTENNA MOVEMENT CAN BE OBSERVED DURING TEST!

Push El UP button.  Antenna elevation reading should increase.  Move until elevation reads 20 degrees.  Place
inclinometer on feed boom tubes.  Inclinometer should indicate that feed boom tubes are 20º above horizontal.
(Note: The feed boom tubes are indicated on the interface drawing and are parallel to the antenna bore sight.) If not,
refer to the controller manual for elevation zero voltage setting.

Press AZ CW and AZ display should increase, and AZ should rotate CW as viewed from above the antenna.

Press AZ CCW and AZ display should decrease.

Press Pol CW and Pol display should increase.
Press Pol CCW and Pol display should decrease, and the feed AZ should rotate CW as viewed from behind the
reflector.

2.5  ELEVATION STOW POSITION SETTING

HAVE SOMEONE OUTSIDE AND ELEVATED SO ANTENNA MOVEMENT MAY BE OBSERVED DURING TEST!

Press mode key to change screens and Select STOW.

2.4  CONTROLLER/POSITIONER VERIFICATION TEST

Содержание 1.2M MVSAT

Страница 1: ...INSTALLATION ASSEMBLY INSTRUCTIONS 1 2M MVSAT Antenna ANTENNA SYSTEMS...

Страница 2: ...iance with any part of this claim procedure may invalidate this warranty in whole or in part THIS WARRANTY IS EXPRESSLY IN LIEU OF ALL OTHER AGREEMENTS AND WARRANTIES ANY IMPLIED WARRANTY OF MERCHANTA...

Страница 3: ...ack 3 6 Azimuth Stow and Limit Switches SECTION 4 Elevation Positioning System 4 1 Elevation Pivot Assembly 4 2 Elevation Linear Actuator 4 3 Elevation Position Feedback 4 4 Elevation Stow and Limit S...

Страница 4: ...he cable around the driver capstan several times before wrapping the larger driven drum The method used to wrap the capstan results a minimum free length of cable The load in the cable on the main dru...

Страница 5: ...t 25 A 3 inch diameter hole should be in the mounting surface The mounting surface must be flat within 005 inch to prevent binding the azimuth bearing after torquing the mounting bolts No obstruction...

Страница 6: ...button Antenna elevation reading should increase Move until elevation reads 20 degrees Place inclinometer on feed boom tubes Inclinometer should indicate that feed boom tubes are 20 above horizontal...

Страница 7: ...no further greasing is required Because of the excess capacity low rpm and low number of cycles no maintenance is required 3 1 AZIMUTH BEARING 3 2 AZIMUTH GEARBOX The azimuth gearbox is a low backlash...

Страница 8: ...e grooved capstan and once around the drum with solid connections on one end and high force Belleville springs on the other end Fig Below One cable has the capacity to withstand a 75mph wind load The...

Страница 9: ...belt from the potentiometer gear The potentiometer may also be electrically zeroed by the controller See pertaining section of the controller manual 3 6 AZIMUTH STOW AND LIMIT SWITCHES The controller...

Страница 10: ...splayed by the controller at the limits may vary 4 1 ELEVATION PIVOT ASSEMBLY The elevation pivot assembly consists of a linear actuator assembly that pivots between the two blades on the AZ EL castin...

Страница 11: ...t the end of the waveguide tube to the OMT The feed OMT is rotated by chain drive assembly and 12 VDC motor Position feedback is from a 10 turn potentiom eter 5 2 FEED The feed assembly consists of an...

Страница 12: ...ter The feed assembly is installed as a complete unit and secured to lower feed bracket The feed horn is mechanically positioned with a template within 1 8 of the theoretical focal point of the reflec...

Страница 13: ...limits and observe cable tracking 7 Inspect cable terminations and tighten springs if more than 010 gap exists between spring sets Tighten with an open end 1 4 wrench and using Visegrips pliers holdi...

Страница 14: ...2MVSAT comes with a manual drive on the azimuth if needed The manual drive is located on the lower right back of casted mount underneath cover plates See attached figure Use a 1 2 socket with extensi...

Страница 15: ...15 SECTION 7 Interface Drawing 1 1 2 13 9 16 31 3 8 21...

Страница 16: ...ts high 110V AC 1 ph 60 Hz 15 amp or 220V AC 1 ph 60 Hz 7 5 amp MECHANICAL Reflector Mount Geometry Polarization Travel Azimuth Elevation Operational Standard Total Polarization Speed Slewing Deployin...

Отзывы: