The installation area must be level, firm and vibration-proof. It must have the
necessary carrying capacity for the weight of the dryer. The weight of the
dryer is specified in the technical data section of the annex.
The dryer should be installed with sufficient spacing at the top, sides, and
rear, in order to be able to carry out maintenance work and change the
desiccant without any hindrances.
The minimum required spacing is 1 m.
If in doubt, the installation site must be inspected by specialists. Contact your
distributor should you have any questions relating to the installation location.
Setup
► Remove the packaging of the dryer.
► Check that the lifting eyebolts are secure in
the holes in the top valve block.
► Attach suitable lifting gear to the transport
lugs.
► Place the dryer at its installation site.
Transporting with crane
Anchoring the dryer
The upright stand profiles of the dryer are provided with pre-drilled anchorage
bores.
► Use suitable attachment material to anchor
the dryer to the floor (see figure).
►
In the case of vibrating floors:
place the dryer on suitable vibration dampers.
Holes on the base of the dryer