
EN
| User Manual
Technical product description
16
BSP-MT 10-95/D3
Pressure build-up phase
After dehumidifi cation the pressure in the
regenerated hollow section vessel is built up to
operating pressure, so that the switchover from
regeneration to adsorption can take place at
operating pressure level.
Pressure build-up
Standby phase (only with the dewpoint-sensing control option)
When in standby phase, the fully regenerated vessel is ready for absorption operation. The
system is switched to this vessel, as soon as the measured dewpoint at the compressed air
outlet has reached the set dewpoint value for switchover.
Switchover
When the drying agent in the adsorbing chamber has taken up a suffi cient level of humidity,
then the switchover between the vessels will be effected between the vessels. Following
switchover, the above-described process is repeated, with the adsorption and regeneration
now taking place in the respective different vessel.
Содержание BSP-MT 10/D3
Страница 2: ......
Страница 53: ...EN User Manual Annex with technical documentation BSP MT 10 95 D3 51 Regeneration in B1 and adsorption in B2 ...
Страница 56: ...EN User Manual 54 BSP MT 10 95 D3 ...
Страница 57: ...EN User Manual BSP MT 10 95 D3 55 ...
Страница 58: ...EN User Manual 56 BSP MT 10 95 D3 ...
Страница 59: ......