9.3.3. EVACUATION OF THE EQUIPMENT
WHEN INSTALLING AN AIR CONDITIONER, BE SURE TO EVACUATE THE AIR INSIDE THE INDOOR UNIT AND PIPES in the
following procedure.
1. Connect a charging hose with a push pin to the Low side of a charging set and the service port of the 3-way valve.
•
Be sure to connect the end of the charging hose with the push pin to the service port.
2. Connect the center hose of the charging set to a vacuum pump with check valve, or vacuum pump and vacuum pump adaptor.
3. Turn on the power switch of the vacuum pump and make sure that the needle in the gauge moves from 0 PSI to 14.5 PSI. Then
evacuate the air approximately ten minutes.
4. Close the Low side valve of the charging set and turn off the vacuum pump. Make sure that the needle in the gauge does not
move after approximately five minutes.
Note: BE SURE TO FOLLOW THIS PROCEDURE IN ORDER TO AVOID REFRIGERANT GAS LEAKAGE.
5. Disconnect the charging hose from the vacuum pump and from the service port of the 3-way valve.
6. Tighten the service port caps of the 3-way valve at a torque of 13.3 lbf with a torque wrench.
7. Remove the valve caps of both of the 2-way valve and 3-way valve. Position both of the valves to “OPEN” using a hexagonal
wrench (5/32”).
8. Mount valve caps onto the 2-way valve and the 3-way valve.
•
Be sure to check for gas leakage.
CAUTION
•
If gauge needle does not move from 0 PSI - 14.5 PSI, in step
above take the following measure:
•
If the leak stops when the piping connections are tightened further, continue working from step
.
•
If the leak does not stop when the connections are retightened, repair the location of leak.
•
Do not release refrigerant during piping work for installation and reinstallation. Take care of the liquid refrigerant, it may cause
frostbite.
24
CS-E18EKU CU-E18EKU / CS-E21EKU CU-E21EKU
Содержание CS-E18EKU
Страница 10: ...4 Dimension 4 1 Indoor Unit Remote Control 10 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...
Страница 11: ...4 2 Outdoor Unit 11 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...
Страница 12: ...5 Refrigeration Cycle Diagram 12 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...
Страница 13: ...6 Block Diagram 13 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...
Страница 14: ...7 Wiring Diagram 7 1 CS E18EKU CS E21EKU 14 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...
Страница 15: ...7 2 CU E18EKU CU E21EKU 15 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...
Страница 16: ...8 1 Indoor Unit 8 Printed Circuit Board 16 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...
Страница 17: ...8 2 Outdoor Unit 17 CS E18EKU CU E18EKU CS E21EKU CU E21EKU ...