12
5.2 Installation and Setting to Work
5.2.1 Preparation of Site and Services
5.2.1.1 Environmental Requirements
It is the customer’s responsibility to ensure that all local building and safety regulations are met.
Ensure that the environmental conditions of the installation site conform to the requirements stated
in the SPECIFICATIONS section of this manual.
5.2.1.2 System Layout
The minimum distance between the back, or side of the casing, and other equipment must be
greater than 30 cm.
Do not place the KMW200CCD close to any other heat-producing equipment.
5.2.1.3 Electrical Services
The electrical supply must conform to the requirements stated in the SPECIFICATIONS section of
this manual.
Locate the electricity supply close to the system and provide:
Phase
L
Neutral
N
Protection PE
The mains plug should be readily reachable by the operator when the equipment has been
installed.
5.2.1.4 Water Supply
Prepare 20 litres of clean distilled water to fill the reservoir.
5.2.2 Setting to Work
The location of connectors on the KMW200CCD is shown in figure 5.2.1.