background image

   CAUTION: Fire Hazard

Before energizing, confirm that all hardware 

is installed as shown on the Installation page.  

Stacking battery terminal hardware in any 

other order can overheat the terminals.

!

900-0213-01-00 REV B

Do not copy or distribute without permission.

Energize/Startup 

Procedures

De-energize/Shutdown 

Procedures

WARNING:  Lethal Voltage

Review the system configuration to identify all possible sources of 

energy.  Ensure ALL sources of power are disconnected before 

performing any installation or maintenance on this equipment.  

Confirm that the terminals are de-energized using a validated 

voltmeter (rated for a minimum 1000 Vac and 1000 Vdc) to verify 
the de-energized condition.

WARNING:  Lethal Voltage

The numbered steps will remove power from the inverter and 

charge controller.  However, sources of energy may still be 

present inside the wiring boxes and other locations.  To ensure 

absolute safety, disconnect ALL power connections at the source.   

WARNING:  Burn Hazard

Internal parts can become hot during operation.  Do not remove 

the cover during operation or touch any internal parts.  Be sure to 

allow them sufficient time to cool down before attempting to 

perform any maintenance.     

To de-energize or shut down the OutBack Power devices:

1. Open the AC circuit breakers.
2. Open the DC circuit breaker for the battery.
3. Open the PV circuit breaker, if present.   
4. Open the ground-fault circuit breaker, if present.
5. Open the FLEXnet DC circuit breaker, if present.
6. Verify 0 Vdc on the DC input terminals of the inverter by placing the

voltmeter leads on        and       .

7. Verify 0 Vdc on the PV charge controller terminals, if present.
8. Verify less than 5 Vac on the AC output circuit terminals

      and       .

9. Verify less than 5 Vac on the AC input circuit terminals

      and       .

2

3

4

4a

4b

Pre-startup Procedures

After opening the AC and DC enclosures:
1. Double-check all wiring connections.  Ensure all torque values are met.

See 

Wiring Data

 on the other side of this sheet.

2. Inspect any enclosures to ensure no tools or debris were left inside.
3. Disconnect all AC loads at the backup (or critical) load panel.
4. Disconnect the AC input to the inverter system at the source.
5. If a mechanical interlock is used, place it in the normal (non-bypass) position.
6. Using a digital voltmeter, verify 12, 24, or 48 Vdc at the battery source. 

Confirm the polarity

.

These instructions assume the use of AC and DC wiring boxes of OutBack Power models.

To energize or start up the OutBack Power devices:

1. Close the DC circuit breaker from the battery bank to the inverter.   
2. Using a digital voltmeter, verify 12, 24, or 48 Vdc on the DC input terminals by placing the

DVM leads on        and       .  Confirm that the voltage and polarity are correct for the inverter 

and charge controller models.  

3. If PV is installed, verify the correct voltage and polarity at the charge controller terminals.
4. Close the ground-fault circuit breaker, if present.
5. Close the PV input circuit breakers, if present.
6. Close the circuit breaker for the FLEXnet DC, if present.
7. Using the system display, perform any necessary programming, particularly for the size of the

AC input source(s).  See Sheet 3 for the Profile Wizard. 

8. The factory default state for all FXR inverters is OFF.  Using the system display, turn the

inverter to the ON state.

9. Using the DVM, verify the inverter AC output on the AC output circuit terminals        and       .   
10. Without closing the inverter system’s AC input circuit breakers:  Using the DVM, test the

voltage of any input AC source(s).

11. Connect the AC source.  Close the inverter system’s AC input circuit breakers.

Using the DVM, verify 120 Vac on the AC input circuit terminals        and       .

NOTE

:  After a brief delay, the inverter’s transfer relay will activate unless the inverter’s

settings have been changed.  Using the system display, verify the input source and the

inverter’s charging function.  After verification, disconnect the AC source.

12. Replace the covers on the AC and DC enclosures.
13. Close the AC output circuit breakers.         Turn on the AC disconnects at the load panel 

and test the inverter’s output while operating loads.

1

2

5

4

2

1

6

5

3a 3b

1

2

2

1

3

6

6

5

4a

4b

1

3

4

Functional Test Points

Battery Negative (–) Terminal

Battery Positive (+) Terminal 

AC H

OT

 I

N

 Terminal

AC N

EUTRAL

 I

N

 Terminal*

AC H

OT

 O

UT

 Terminal

AC N

EUTRAL

 O

UT

 Terminal*

*Terminals 

3b 

and 

4b 

are electrically common. 

1

2

3a

3b

4a

4b

3a

3b

4a

4b

1

2

4a

4b

1

2

3

2

4

1

1

5

3a 3b

3a

3b

   CAUTION: Equipment Damage

Incorrect battery polarity will damage the equipment.

!

1

2

NOTES:  

o

o

If a system display is not present, the inverter must be

turned off or on using an external switch or the 

O

N

/O

FF

 jumper.

 

See the 

Installation Manual

 for more instructions.  

1

If any of these tests do not function as described, or for other

 

troubleshooting, see the 

Operator’s Manual

.  

2

Отзывы: