www.orte.pl
9
8.
With 6 screws M6 fasten the hearth shield (OP) to the bottom metal pieces and the support as in fig. 6.1.
ATTENTION: Do not drive the screws fully into the bottom metal pieces. The top metal pieces will be put on
them later.
9.
Fasten the top metal pieces together (BGL and BGP) with 2 screws M6 (ŚM6) (fig. 6.3) and then push them
onto the screws M5 of the hearth shield (OP) as in fig. 6.1. The 4 screws M5 (ŚM5) must also be driven into
the sides of the top metal pieces as in fig. 6.2, leaving approx. 2 mm clearance between the head of the screw
and the top metal piece. They will be used for hanging the top door (DG) – see fig. 10.
Fig. 6
10.
Fasten the centring ring (PC) to the chimney (K) with 3 bolts. Mount the heater cap (CO) with 3 screws M5 as
in fig. 7.
Fig. 7