Ormazabal CTC Скачать руководство пользователя страница 5

 

 

GENERAL INSTRUCTIONS FOR CTC 

UNDER POLE COMPACT 

TRANSFORMER SUBSTATION  

IG-086-GB    

version 02 

11.07.2007

 

 

Page 5 of 20

 

1.1. PREFABRICATED ENCLOSURE 

It consists of: 

 

  Concrete monoblock prefabricated construction with IP339 rating, complying with the 

UNE 20 324 standard. 

 

 Removable 

cover. 

 

  One  front  access  door  to  the  Low  Voltage  Board  (LVB)  with  dimensions  of             

975 x 970 mm. The one leaf access door is provided with a system that allows to fix it 
at 90º and avoids accidental closing. There is a physical barrier from the LVB access 
area to the transformer access area. 

 

  Two side doors with dimensions of 982 x 1320 mm that allow access to the 

transformer area. Both doors can be unlocked from the LVB compartment. 

 

  Two side grilles over

 

each of the transformer access doors, for air intake / exhaust, 

allowing optimal ventilation. They are provided with a mosquito netting of 6 mm 
maximum mesh. 

 

  Two  cable  access  areas,  one  for  MV  cable  incoming,  with  dimensions  of                   

400 x 190 mm, at the 

CTC 

TS

 

back bottom and another one for LV cable outgoing, 

with dimensions of 440 x 190 mm, at the front bottom. 

 

  Dielectric liquid collecting pit with a capacity of 400 l. 

 

  Electrical warning plate. 

 

1.2. TRANSFORMER 

  Transformer up to 250 kVA, 36 kV

[1] 

series. 

 

1.3.  LOW VOLTAGE BOARD 

The 

CTC

 Transformer Substation can be supplied with the Low Voltage Board (LVB) 

installed at the factory. 

 

The LVB consists of a metal frame that supports the protection functional unit, which is made 
up of vertical fuse holder bases BTVC. The busbar functional unit, made up of horizontal 
bars, is fixed on these bases. To identify the horizontal bars different colours are used. 

                                                 

[1] 

This functional unit is included in the 

CTC

 TS only upon request. 

Содержание CTC

Страница 1: ...TRANSFORMER SUBSTATION General Instructions LIB 11 07 2007 Secondary Distribution Switchgear Primary Distribution Switchgear Protection and Automation Distribution Transformers IG 086 GB version 02 T...

Страница 2: ...ccording to current legislation This must be carefully taken into account because the safe and proper operation of this equipment depends not only on its design but on circumstances which are generall...

Страница 3: ...3 2 PLANNING 9 3 3 HANDLING 9 3 4 DIMENSIONS OF THE EXCAVATION 10 3 5 LEVELLING PROCESS 11 3 6 PROTECTION AND EARTHING CIRCUIT 12 3 6 1 Protection Earth Connection 12 3 6 2 Service Earth Connection 12...

Страница 4: ...3 Low Voltage Board LVB 1 OVERVIEW AND MAIN CHARACTERISTICS Ormazabal s CTC is an Under Pole Compact Transformer Substation designed to be installed on the surface with outdoor operation complying wit...

Страница 5: ...nsformer access doors for air intake exhaust allowing optimal ventilation They are provided with a mosquito netting of 6 mm maximum mesh Two cable access areas one for MV cable incoming with dimension...

Страница 6: ...ons and weights of the CTC Transformer Substation are as follows Total 2080 Height mm View 1600 Length mm 1330 Depth mm 2170 Without Transformer 2000 Enclosure With Transformer 4600 Weight kg Cover 50...

Страница 7: ...the truck s platform to the CTC TS base must be at least 80 mm The enclosures are loaded in such way that the door on the short side faces the truck s cab Once the CTC TS has been placed on the palle...

Страница 8: ...rotected with elastic plastic tape wound around several times in order to avoid water filtering in the enclosure during transport Two boards of 2000 x 150 x 20 mm will be used to rest the CTC Transfor...

Страница 9: ...he CTC TS is provided with DEHA hooks that used with a lifting beam slings and adequate hooks ensure that the lifting operation is as balanced as possible For the transversal balancing a lifting beam...

Страница 10: ...s must not be exceeded The maximum burying height is 480 mm measured from the base of the Transformer Substation These levels will be adapted to the earth network solution taken for each case accordin...

Страница 11: ...velled sand to avoid an uneven base The installation operation involves positioning the CTC TS in the excavation made for this purpose and connecting the LV and MV cables as well as the external earth...

Страница 12: ...ed to the protection earthing circuit metallic parts which is finally connected to the protection disconnection box 3 6 2 Service Earth Connection The service earthing circuit zero sequence earth conn...

Страница 13: ...er of the facilities shall implement at least one of the additional safety measures provided in this instruction in order to reduce the risks to persons and assets The recommended tightening torque fo...

Страница 14: ...ver with four chains of the same length 3 Place the cover on the floor on two boards 4 Put the transformer into the CTC TS with the tow truck 5 Place the cover on the CTC TS and connect the earth cabl...

Страница 15: ...he steps below 1 Open the door of the CBT TS compartment and put it in its fixed position 2 Install signals on the working area 3 Activate the locking of the door grille of the transformer compartment...

Страница 16: ...losure under the access door to the LVB To open a hole just hit it with a hammer 3 8 1 Connection of the MV Cables to the Transformer If the transformer is fitted with 24 kV plug in bushings it is rec...

Страница 17: ...per DIN 46 235 The connection is made directly on the busbar with M10 screws 4 3 8 3 Connection of the Cables to the LVB Outgoing The LV cable outgoings are made with the LVB s BTVC bases screws 4 To...

Страница 18: ...oor on two boards 8 Open the LVB compartment door see figure 3 8 9 Earth the circuit 10 Activate the locking of the door grille of the transformer compartment 11 Open the transformer compartment doors...

Страница 19: ...lly it might be advisable to check and grease the locks There should be no obstacles signs plants etc on the ventilation grilles of the prefabricated enclosure 5 ADDITIONAL INFORMATION 5 1 ACCESSORIES...

Страница 20: ...Hoja 20 de 20 TECHNICAL COMMERCIAL DEPARTMENT www ormazabal com...