  e. When the floats and filter cartridge are out of the tank, verify the 

handles are long enough for easy access. If they are not, adjust 
them to the necessary length.

  f.  Reinstall the cartridge in the pump vault. Leave the float assembly 

out of the tank or basin for use during pump run testing.

7.

 Effluent pump: 

Verify the pump is easy to remove for service and 

maintenance and that the pump flow rate and voltage are correct. 
The ability to easily remove the pump is essential and depends upon 
careful installation in accordance with the instructions provided in 
Appendix B. Set components on a plastic tarp or plastic sheeting 
when they are out of the tank.

  a. Switch the pump breaker(s) 

in the control panel to the 
“OFF” position.

  b. Verify the ball valve and 

cam-lock fitting or union on 
the discharge assembly is 
within 24 inches (610 mm) 
of the top of the riser. 

  c. Close the ball valve on 

the discharge assembly if there is one and disconnect the 
discharge assembly at the union or cam-lock fitting. 

  d. Verify there is enough slack in the pump cord for easy removal.

  e. Pull the pump out of the vault by the discharge assembly and 

remove the pump from the tank.

  

WARNING:

 Lifting or lowering the pump by the cord can 

damage the pump and cord.

  f.  Check the voltage and phase values on the pump nameplate. 

Write them down in the start-up report. If there are pump motor 
stickers on the inside of the control panel door, check to see if 
they match the pump nameplate.

  

WARNING:

 

If the pump does not match the panel voltage and 

phase requirements, do not turn on the pump breakers.

  g. Reinstall the pump if the pump matches the panel voltage and 

phase requirements.

  h. Reconnect the discharge assembly at the union or cam-lock fitting 

and open the discharge assembly ball valve.

  i.  Switch the pump breaker(s) in the control panel to the “ON” position  

when finished. 

Inspection Points – Pumps

When the panel has been inspected and powered up, the float inputs 
have been tested, and all pump voltage and phase information has been 
verified, the pump(s) can be powered up and tested.

1.

 Manual pump operation:

  a. Switch the pump 

breaker(s) in the control 
panel to the “ON” position.

  b. Measure the static 

voltage of the pump(s) 
and enter the value(s) on 
the start-up checklist.

  c. Toggle the pump  

“AUTO-OFF-MAN” switch to “MAN.” The motor contactor will 
visibly and audibly engage at this point. If the motor contactor 
does not engage, check for an “RO” alarm condition. If there is 
no alarm condition, refer to the wiring diagram and verify the 
connections on the control circuit were properly terminated.  

  

WARNING: 

There is no motor protection in TCOM panels and 

panels without “RO” alarms. Before running a pump, always verify 
that there is sufficient liquid in the tank or basin.

  

NOTE:

 Refer to the “General Operating Instructions” section of the 

VCOM control panel documents to perform the “Manual Test” if 
you are starting up a pump controlled by a VCOM panel.

  d. Verify pump motor operation by checking the discharge plumbing 

assembly for vibration. 

 

– No vibration in the discharge plumbing assembly indicates a 

pump wiring issue. Check the pump voltage and pump wiring 
terminations in the panel and in the splice box. Wires may be 
incorrectly terminated or wire insulation may be causing faulty 
contact between the wire and terminal lug. 

 

– Vibration in the discharge plumbing assembly with low or no 

flow from the pump indicates closed valves or line breakages. 
On duplex pumping systems with two discharge plumbing 
assemblies connected together to a single line, verify that there 
are check valves on both pumps and that they are operating 
correctly. On three-phase systems, verify L1, L2 and L3 are 
wired correctly. A quick way to identify if the pump is wired 
correctly is to watch for clockwise torsion in the discharge 
plumbing assembly when the pump is first turned on. 

Inspection Points (continued)

Содержание AdvanTex AX100

Страница 1: ...Start Up and Maintenance of AdvanTex AX100 AX20 Commercial Wastewater Treatment Systems AdvanTex O M MANUAL 800 348 9843 541 459 4449 www orenco com www vericomm net Orenco COMMERCIAL MANUAL O M...

Страница 2: ...on and treatment is our only job When you purchase an Orenco system you can be confident you have chosen the best equipment available Assistance In addition to providing quality equipment Orenco pride...

Страница 3: ...ints Recirculation Blend Tank 13 Inspection Points AdvanTex Filter Pods 13 Inspection Points Vent Fan Assembly 14 Inspection Points Distribution Valve 14 Housekeeping 14 Maintenance Tools Equipment an...

Страница 4: ...ion from AdvanTex filtrate returning from the flow splitter basin The harmless nitrogen gas is released freely back into the atmosphere Recirculation Blend Tank The recirculation blend tank reduces th...

Страница 5: ...nstallation of all equipment and the availability of power phone line and water at the site The AdvanTex Dealer is expected to be on site and is either performing the start up or acting as a coordinat...

Страница 6: ...tion Site drainage Verify that all riser lids external splice box lids and AX pod lids are level and above grade Serviceability Verify that there is a minimum of two feet of space between AX pods Chec...

Страница 7: ...control panel to assure proper system operation and component longevity 4 Power supply voltage Make sure the panel breakers are switched off and check the power supply voltage at the panel On 120 V pa...

Страница 8: ...er Inspect the riser attachment and rubber grommets for a watertight seal 4 Splice box Inspect the splice box for correct wiring and the use of waterproof splice nuts If there is water in the splice b...

Страница 9: ...TCOM control panels d Check the float settings provided in the plans against the actual float settings If the plans don t provide float settings and the engineer or system designer is unable to provi...

Страница 10: ...r cam lock fitting and open the discharge assembly ball valve i Switch the pump breaker s in the control panel to the ON position when finished Inspection Points Pumps When the panel has been inspecte...

Страница 11: ...3200 3 5 3 9 PF500512 5 4 6 2 PF100552 3 6 3 8 PF500532 2 6 3 0 PF100712 7 8 8 4 PF50053200 3 2 3 7 PF10073200 4 9 5 2 PF500534 1 3 1 5 PF100752 5 8 6 2 PF500552 3 3 3 9 PF101012 9 0 9 8 PF500712 7 3...

Страница 12: ...ur system before testing d Lower the float assembly into the tank and clip the float assembly into the float bracket Timed dose a Toggle the AUTO OFF MAN switch to the AUTO position b Record the timer...

Страница 13: ...of 9 inches 229 mm from the normal liquid level to the RO float Inspection Points AdvanTex Filter Pods Your system may include AX100 filter pods shown or AX20 filter pods For AX20 inspection points se...

Страница 14: ...location of all distribution valves in the system 1 Verify liquid level Make sure that the tank or basin that you are pumping from has sufficient liquid to perform the test WARNING There is no motor...

Страница 15: ...r gloves Trash bags Routine Inspection and Maintenance Biotube filter cradle OM BIOTUBECRADLE Beakers or bottles Calculator Channel lock pliers Dissolved oxygen DO meter or colorimetric ampoules 3 16...

Страница 16: ...istribute upon request To request multiple copies of this manual contact Orenco Systems Inc at 1 800 348 9843 With preventive maintenance and periodic inspections the wastewater treatment system will...

Страница 17: ...r biological growth on the spray nozzles Observe and measure the residual pressure Refer back to the Start up Operation section for initial measurements of residual pressure If the observed residual p...

Страница 18: ...E Turn the laterals in the AdvanTex treatment unit 180 degrees so the spray nozzle turbines face up prior to flushing to prevent nozzle clogging while material is being pushed along the lateral to the...

Страница 19: ...Recommended Activity Period Activity Visual Inspection of Tank Liquid Levels 1 Check Biotube Effluent Filters Clean as Required 1 Check Biotube Pump Vault Filters Clean as Required 1 Record Elapsed Ti...

Страница 20: ...itself Test the automatic function of the system as shown in the Start up Operation section of this manual to verify proper operation c Faulty floats If after checking the circuit breakers fuses and...

Страница 21: ...umping downhill A system will not necessarily siphon every time it operates It is dependent on the system design A siphoning system can be retrofitted with an anti siphon valve Most siphoning problems...

Страница 22: ...he splice box lid being careful not to drop the screws into the tank If the splice box was submerged or if there is a crack in the conduit there may be water in the splice box If this is the case remo...

Страница 23: ...______________________ __________________________________________________ __________________________________________________ __________________________________________________ ________________________...

Страница 24: ...________ __________________________________________________ __________________________________________________ __________________________________________________ ______________________________________...

Отзывы: