Installing the Switch
29
Preparing the Chassis
After unpacking the switch chassis and components, mount the switch chassis and
cable management hardware into the rack. Perform the tasks in the following order:
Note –
The illustrations in this topic describe the switch being installed at the
middle position for better clarity. Install the first switch in the rack at the bottom
position for rack stability.
■
“Install the Rail Assemblies in the Rack” on page 29
■
“Install the Cable Trees” on page 32
■
“Install the Cable Curves” on page 38
■
“Install the Chassis in the Rack” on page 39
Related Information
■
“Understanding the Installation” on page 15
■
“Installing the Components” on page 63
▼
Install the Rail Assemblies in the Rack
There are three positions to install the switch into the rack, bottom, middle, and top.
The rack does not accommodate more than three switches.
Note –
For this procedure, the term
cabinet holes
refers to the holes in the posts of the
cabinet. For the Sun Rack II cabinet, these holes are square. The holes are numbered
from 1 starting at the very bottom. Hole 2, 3, 4, and so on, are the second, third,
fourth, and so on, hole from the bottom. The numbering scheme printed on the posts
is not used.
Note –
If you are installing fewer than three switches, favor the bottom and middle
positions.
Содержание Sun Datacenter InfiniBand Switch 648
Страница 1: ...Sun Datacenter InfiniBand Switch 648 Installation Guide Part No 820 7738 12 May 2010 Revision A ...
Страница 8: ...viii Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...
Страница 134: ...124 Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...
Страница 140: ...130 Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...