Installing the Switch
63
Related Information
■
“Inspect the Fabric Card Chassis for Installation” on page 53
■
“Inspect the Line Card Chassis for Installation” on page 58
▼
Inspect the InfiniBand Cable Connectors for Installation
1. Identify the prerequisite and subsequent tasks you must perform in
conjunction with this procedure, to install the switch.
See the table in
“Installation Sequence” on page 20
2. Verify that the shell is not bent and is parallel to the inner boards.
3. Verify that there are no contaminants inside of the connector.
4. Verify that the retractor strap adequately operates the hooks.
5. Install the components.
See
“Install the Midplane Stiffener” on page 64
Related Information
■
“Inspect the Line Card CXP Connectors for Installation” on page 60
Installing the Components
After inspecting the components, perform these task in the following order to install
the components into the switch chassis:
Step
Description
Links
1.
Install the midplane stiffener.
“Install the Midplane Stiffener” on page 64
2.
Install the fabric cards or fabric card
fillers.
“Install the Fabric Cards or Fabric Card
Fillers” on page 67
3.
Remove the midplane stiffener.
“Remove the Midplane Stiffener” on
page 70
4.
Install the line cards or line card
fillers.
Содержание Sun Datacenter InfiniBand Switch 648
Страница 1: ...Sun Datacenter InfiniBand Switch 648 Installation Guide Part No 820 7738 12 May 2010 Revision A ...
Страница 8: ...viii Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...
Страница 134: ...124 Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...
Страница 140: ...130 Sun Datacenter InfiniBand Switch 648 Installation Guide May 2010 ...