3.7
First commissioning
ATTENTION!
Before commissioning the machine check all screws, fixtures resp. safety devices and
tighten up the screws if necessary!
WARNING!
Risk by using improper tool holders or operating them at inadmissible speeds.
Only use the clamping materials (e.g. drill chuck) which had been delivered togetherwith
the machine or as optional equipment offered by OPTIMUM.
Use the working clamping materials only in the provided admissible speed range.
Workpiece clamping materials must only be modified according to the recommendations
of OPTIMUM or of the clamping material manufacturer.
WARNING!
When first commissioning the drilling machine by inexperienced staff you endanger
people, the machine and the equipment.
We do not take any liability for damages caused by incorrectly performed
commissioning.
„Qualification of personnel“ auf Seite 10
3.7.1 Warming up the machine
ATTENTION!
If the drilling machine and in particular the drilling spindle is immediately operated at
maximum load when it is cold it may result in damages.
If the machine is cold such as e.g. directly after having transported the machine it should be
warmed up at a spindle speed of only 500 1/min for the first 30 minutes.