25
Multi Dwelling Units (MDUs)
When Openreach is to install the ONT and battery
backup, 3m of cable is required at the splitter
location and 1m (2m if non-connectorised cable)
at the ONT end of the installation.
Each apartment will require a designated
connectorised internal fibre cable run in a
continuous fault-free condition from the
designated ONT location within the apartment
to the splitter box within the riser.
At the splitter locations the cable should be
clearly marked with the apartment number and
left safely coiled within the riser.
• Install a flush mounted double back box at the
desired ONT location.
• Install the connectorised fibre cable from this
point to the designated riser termination point.
• Ensure there is 1m of spare connectorised fibre
cable protruding from the back box. (2m if non-
connectorised cable)
• Push some of the spare cable back into the
wall void and coil the remainder inside the
back box, taking care not to damage the
connectorised end.
• Install blanking plate or brushed face plate to
protect cable ready for provision of ONT nearby.
Option where Openreach installs the equipment
Your FBC will advise of all cable marking/
labelling and will check for this when ‘calling
off’ the work.
IET wiring regulations shall be followed.
External cables can run to a maximum of
2m from the internal building entry point.
From this point onwards, all cables must meet
current fire regulations. The alternative is to
house all cables in metallic trunking.
Internal fibre cable must not be bent beyond
its minimum radius. If it has been damaged
or there is evidence of kinking it shall be
discarded. Your FBC will advise on replacement
of the cable.
Care shall be taken to avoid stretching cable/
tubes through installation. If cables are
damaged this way you will be required to
replace them.
Bends in fibre cable shall be kept to a minimum and
the installation of trunking, cable trays/grids shall
not compromise the bending radii.
Fibre cable containing no metal parts can be run on
shared trays.
Plate cable fixings with cable ties must be used to fix
fibre cable direct to walls to avoid it being damaged.
Under no circumstances shall cable or tubing be
secured or supported to the suspended ceiling
hangers or under floor support legs.
It is the developer’s responsibility to provide
fire stopping on completion of the cable/
tubing installation.
Openreach networks must not interfere with or
be interfered with by other services within the
riser or any other shared space. e.g.
• Un-insulated hot water pipes.
• Unscreened mains cables.
• Fluorescent lighting.
• Heavy duty switch gear.
A wayleave may be required from the
building owner prior to installing apparatus
in common areas.
Remember you may need to order copper lines
for commercial properties, for example lift lines.
How to build a fibre network - version 7.1
Содержание ONT
Страница 1: ...fibre network Developer Guide Version 7 1 August 2018 How to build a ...
Страница 21: ...21 Multi Dwelling Units MDUs Maisonettes How to build a fibre network version 7 1 ...
Страница 22: ...22 Openreach Developer Guide Multi Dwelling Units MDUs Flat over garage ...
Страница 23: ...23 Multi Dwelling Units MDUs Chalets How to build a fibre network version 7 1 ...
Страница 24: ...24 Openreach Developer Guide Multi Dwelling Units MDUs Modular Passive homes ...
Страница 27: ...27 Commercial units SME within an MDU How to build a fibre network version 7 1 ...
Страница 28: ...28 Openreach Developer Guide Commercial units Commercial unit within a commercial only site ...
Страница 50: ...50 Openreach Developer Guide Notes ...
Страница 51: ...fibre network How to build a ...