6.
Develop the film and visually check the film to determine whether the field
sizes are within the following specifications:
FIELD SIZE
RING
NORMAL
A
MAG
B
7.
Verify that the minimum field size is less than 5 cm
2
.
8.
Use a ruler and verify the center of the image appears on the sheet of film
(in both the X and Y axis) within 20 mm or 13/16-inch.
9.
If the films do not meet the specification, refer to the Beam Alignment
procedure in the Compact / Series 7600 Service Manual.
Complete Paper Work
1.
Make sure that all portions of the Installation Report/Checklist are
completed.
2.
Make sure the beam alignment films are properly labeled.
3.
Distribute the copies of the FDA form 2579 to the appropriate individuals
as outlined on page 1.
4.
Return the Installation Report/Checklist to OEC immediately.