© NOVATEC, Inc, 2018 All Rights Reserved 10 Document: SVP IM 7 FEB 2018
8 ELECTRICAL INSTALLATION
Connect the proper power supply (check nameplate) through a main line disconnect switch
(not supplied) to terminal connections L1, L2, L3 and ground into the MVP control cabinet
that contains the motor starter. This is the only power connection required since the motor is
pre-wired at the factory. See schematic on the next page. See FLA specification table on
page 16.
Connect control wiring from the conveying system control panel to the same electrical
enclosure as shown on the wiring schematic for the conveying system control panel. Verify
the correct rotation of the motor with the directional labels on the pump assembly.
3 Phase Electrical Power:
1. Verify nameplate information on the pump frame assembly
2. Use the FLA/KVA chart on page 15 as a guide
3. A nominally rated 3 phase disconnect switch must be provided
4. All connections must be provided in strict adherence to local and national codes by a
qualified electrician.