90 mm max
CAUTION!
• A wrong connection can cause faults or danger; therefore follow scrupu-
lously the connections set out.
• Perform the connection operations when the electricity is off.
To connect the gear motor to the control unit, proceed as follows:
01.
Remove the lid of the gear motor as shown in
fig. 12
;
02.
Slacken the gearmotor cable clamp, thread the connecting cable through
the hole and connect the three electric wires as shown in
fig. 13
;
03.
Replace lid on gear motor.
To check the connections, direction of rotation of the motor, phase shift in the
movement of the leaves and setting the limit switch, refer to the instructions
manual of the control unit.
IMPORTANT
– With a gate configured with opening towards the outside invert
the power supply wires with respect to the standard installation.
This is the most important phase in realising the automation to guarantee max-
imum safety. The inspection can be used also to periodically check the devices
which make up the automatism.
The inspection of the entire system must be performed by expert and qual-
ified staff
who must take responsibility of the tests requested, depending on
the risk involved and to check compliance of what is set out by laws, rules and
regulations and in particular all the requirements of regulation EN 12445 which
establishes the testing methods to verify gate automatisms.
• Inspection
Each single component of the automatism, for example sensitive edges, pho-
tocells, emergency shutdowns, etc. requires a specific inspection phase; for
these devices follow the procedures shown in the respective instruction manu-
als. For inspection of the gear motor follow the operations below:
01.
Check that everything in this manual and in particular in chapter 1 has been
rigorously complied with;
02.
Unblock the gear motor as shown in
fig. 14
;
03.
Check it is possible to manually move the leaf when opening and closing
with a force no greater than 390N (approx. 40 kg);
04.
Block the gear motor and connect the electrical power supply;
INSPECTING THE AUTOMATION
5
ELECTRICAL CONNECTIONS
4
10
11
9
www.metalines.com