Nibe VEDEX 3300 Скачать руководство пользователя страница 10

8

VEDEX 3300

For the Installer

Assembly

VEDEX 3300 has inlets for primary air at the front and 
secondary air on the sides of the boiler. Therefore, always 
leave a space of at least a metre from combustible mate-
rial. In unfavourable cases “puffs” from combustion can 
discharge sparks.

Turbulators

Six turbulators are supplied with boiler. These are located 
in the ducts in the boiler’s convection part as illustrated. 
The turbulators affect the turbulence of the flue gases, 
which means that a greater amount of energy is trans-
ferred to the boiler water. The temperature in certain 
chimneys may become so low that there may be a risk 
of condensation build-up in the smoke duct. To increase 
the temperature in the chimney the turbulators can be 
removed, one at a time as illustrated. For each turbulator 
that is removed, the flue gas temperature rises from the 
boiler by 15 - 25°C.
Remove the turbulators in number order until the flue gas 
temperature in the chimney is correct.

LEK

1

3

4

5 6

2

General information for the installer

1

3

4

5

6

2

66

Boiler room

The boiler room must be built in accordance with applica-
ble building regulations.
Provision for good air supply. The boiler room’s air intake 
must be as large as the smoke pipe duct.

Chimney

VEDEX 3300 has a vertical flue pipe connection with an 
external diameter of 133 mm. Angled flue pipe supplied as 
standard.
Different chimney heights are required depending on ver-
sion. In addition, a number of other factors, for example, 
wind and terrain conditions, nearby buildings etc, can 
affect the draught conditions of the chimney. Minimum 
chimney draught for satisfactory wood firing is 15 Pa.
The following table showing several different versions of 
chimney is a recommendation, however, the aforemen-
tioned factors must also be taken into consideration.

Material

Area

Minimum 
height

Steel pipe

Ø 125 mm

5.0 m

Brick

140 x 140 mm

5.0 m

Many older boilers have the flue duct located down below 
and will have been connected to the chimney near to the 
floor. If the new boiler is to be connected higher up on the 
chimney the lower non-active part of the chimney pipe 
should be filled with sand or similar.

EX 

Minimum 5 m

vid vedeldning

Fyllning

Undertryck i skorstens-

anslutningen minimum

1,5 mmVP (15Pa).

Ensure that sweeping can be carried out in 

accordance with the applicable regulations. 

If in doubt, contact a chimney sweep.

Note!

The flue gas temperature must not drop 

below 65°C 0.5 m below chimney opening.

Note!

General information for the installer

Minimum 5m 
during wood firing

Chimney connection 
vacuum minimum 
1.5 mmVP (15Pa).

Filling

Содержание VEDEX 3300

Страница 1: ...MOS GB 0733 1 VEDEX 3300 M10528 INSTALLATION AND MAINTENANCE INSTRUCTIONS VEDEX 3300 LEK...

Страница 2: ......

Страница 3: ...__________________________ 9 Pipe installation Connection_ ______________________________________ 10 Flue gas thermometer______________________________ 10 Filling_ ____________________________________...

Страница 4: ...bers in brackets refer to the section Component locations The boiler is designed for houses with water borne heating and is environmentally approved for accumulator tank firing This appliance is not i...

Страница 5: ...of wa ter heater size or the length of coil Abbreviations HW Hot water CW Cold water S V Safety valve AV Shut off valve WH Water heater EX Expansion vessel SV1 Shunt valve SV2 Mixer valve CP1 Charge p...

Страница 6: ...stops the fan when the boiler temperature exceeds the set value Charge thermostat Thisthermostat starts and stops the charge pump at the set value 20 100 40 80 60 0 120 2 1 bar 3 0 4 Indicator lamp f...

Страница 7: ...door 66 pulling up the turbulator and brushing clean This should be done a few times between chimney sweep visits For optimum combustion and efficiency the boiler s sec ondary combustion chamber shou...

Страница 8: ...fter the supply of secondary air Primary air control The control damper on the front of the boiler is used to distribute the air supply to the hearth In the left position the air supply is from the to...

Страница 9: ...of wood are used stack these over the grate hole to wards the rear wall When the wood in the boiler has been burned and the flue gas temperature drops to 80 85 C and a mini mal bed of embers remains...

Страница 10: ...take must be as large as the smoke pipe duct Chimney VEDEX 3300 has a vertical flue pipe connection with an external diameter of 133 mm Angled flue pipe supplied as standard Different chimney heights...

Страница 11: ...amic grate Place the ceramic inserts in through the filler door First position the front stone B Then position the rear stones C and D followed by stones E and F Flame trough Open the combustion chamb...

Страница 12: ...e component parts Note Flue gas thermometer VEDEX 3300 is supplied with an enclosed flue gas ther mometer which must be installed in the flue gas door outlet Filling Fill the boiler with water using a...

Страница 13: ...the electrical panel for this type of docking See Electrical installation Reconnection When the boiler s temperature and flue gas temperature exceeds the set temperature on the relevant thermostat th...

Страница 14: ...nnection also the charge pump Electrical circuit diagram Electrical installation Laddpump Max thermostat 3 only controls the boiler s fan and charge thermostat 19 only controls the external charge pum...

Страница 15: ...070 590 85 20 40 1115 1150 170 R32 inv 125 159 inv R25 inv R32 inv 15 utv R25 inv 15 utv 370 450 R25 inv min 250 515 180 125 1275 Minsta avst nd till v gg 250 mm 125 70 1320 Technical specifications T...

Страница 16: ...specifications 45 42 40 3 36 19 2 Component location boiler section Component location front panel 133 utv R25 inv 15 utv R25 inv 125 45 19 3 42 40 2 36 83 22 22 66 96 83 66 96 33 81 82 33 81 82 100...

Страница 17: ...3 Front panel 36 Indicator lamp operation 40 Thermometer 42 Manometer 45 Control switch 64 Sight glass 65 Filler door 66 Soot door for convection part 68 Combustion door 81 Flow line R32 int 82 Expans...

Страница 18: ...cessories LEK LEK LEK Charger pack 1 Part no 089 872 Contents 1 x non return valve connection 25 1 x charge pump 6 mvp with shutoff valves 1 x shunt valve for heating system connection 25 1 x circulat...

Страница 19: ...ler water volume 65 litres Voltage 230 V Average output during wood firing 33 kW Wood magazine volume 95 litres Wood magazine width 300 mm Wood magazine depth 550 mm Filler door width 300 mm Filler do...

Страница 20: ...wice a year for optimum function and a long serv ice life Check that the boiler is off and that no embers are in the combustion chamber Disconnect the fan from the electrical socket on the boiler Remo...

Страница 21: ...into the flue gas fan when sweeping use the supplied cover plate as follows Remove the soot door Insert the cover plate over the hole as illustrated Reinstall the soot door to prevent soot exiting wh...