Join the mounting rails

Mounting rail

2 mm

Joint

Rivet

Slide the joint section with rivets into the mounting rail
until it catches firmly on the rivet (A). Slide the next
mounting rail in until it also catches on the rivet (B).
Leave a space of 2 mm to compensate for linear expan-
sion.

Installing solar panels in the first (bottom) row

Mounting rail

Assembly clamp

90°

Caution

The assembly clamps can be twisted and are
adapted for use both at the outer edges and
between the solar panels.

1.

Position the first solar panel on the mounting rail.

2.

Click the assembly clamp into the first (bottom) row
5 mm from the end of the mounting rail.

3.

Secure the solar panel with the assembly clamp
screw, tighten to 8 Nm.

4.

Click the assembly clamp into the installation rail on
the right-hand side of the solar panel. Slide the as-
sembly clamp towards the solar panel and connect.

5.

Position the second solar panel on the mounting rail
and move the solar panel towards the assembly
clamp. Connect the cable to the previous solar panel.
Secure the wiring between the solar panels.

6.

Tighten the assembly clamp, tighten to 12-15 Nm.

7.

Install further solar panels according to point 4 to 6.

8.

After the last solar panel in the row 1 has been posi-
tioned on the mounting rail and connected, the as-
sembly clamp is clicked into the mounting rail from
the right. Minimum distance between the assembly
clamp and the end of the mounting rail is 5 mm.

9.

Secure the solar panel with the assembly clamp
screw, tighten to 8 Nm.

Caution

Secure the wiring between the solar pan-
els.

Caution

Take the return cable when installing the
panels. See section Electrical connec-
tion/Cable routing

Caution

Measure the voltage at the connected
panels on the roof before removing any
scaffolding.

Install the following rows in the same way.

NIBE PV Solar cell pack-

age

Chapter 4 | Mounting

14

Содержание PV Solar

Страница 1: ...IHB EN 1841 2 431707 INSTALLER MANUAL NIBE PV Solar cell package...

Страница 2: ......

Страница 3: ...e 8 3 Installation 8 General 9 Installation and positioning 10 4 Mounting 10 Installing solar panels in several groups 15 5 Electrical connection 15 Outline diagram 20 6 Maintenance 20 Service 21 7 Te...

Страница 4: ...e hazards involved Children shall not play with the appliance Cleaning and user maintenance shall not be made by children without supervision Rights to make any design or technical modifications are r...

Страница 5: ...Improper disposal of the product by the user results in administrative penalties in accordance with current le gislation COPYRIGHT The manufacturer retains the copyright for this manual These instruc...

Страница 6: ...ed That the solar panels in particular are undamaged Handling Caution Avoid knocks and mechanical damage to the solar panel Do not lift the solar panels by the connections Do not place the solar panel...

Страница 7: ...luded 4 4 pcs PV cable with pre installed connectors 7 metres 2 pcs PVI INVERTER 10 XX LEK Inverters 1 pcs EME 20 1 pcs CEILING BRACKET PRM XX 20 20 PCS AVAILABLE FOR FIVE DIFFERENT CEILING TYPES Tile...

Страница 8: ...evaluation of whether these could mean increased loads The solar panels must be installed so that snow drifts from snow guards or caused by special conditions in the installation location cannot occur...

Страница 9: ...50 900 1000 1000 1000 1050 1050 900 900 950 950 950 800 800 850 90 1200 South Source SMHI Using the diagram and the map one can estimate the annual value of the solar radiation falling on those sur fa...

Страница 10: ...to install some panels This means that you have extremely good flexibility al lowing attractive roof installation If you need a larger installation it is perfectly possible to expand it In this case y...

Страница 11: ...e sufficient NOTE If there is not a sufficiently stable substructure such as tongued and grooved boards or roof trusses to allow a durable installation the roof must be reinforced Roof bracket stainle...

Страница 12: ...spacer plate must be made of a water and weather resistant material not supplied Adapting roof tiles Use an angle grinder or hammer to make a cut out in the part of the roof tile that covers the roof...

Страница 13: ...oach bolt with M10 nuts Caution The coach bolt should be installed from under neath before the plate is mounted on the roof Caution Never use the installed roof brackets as a lad der Installing the mo...

Страница 14: ...clamp towards the solar panel and connect 5 Position the second solar panel on the mounting rail and move the solar panel towards the assembly clamp Connect the cable to the previous solar panel Secur...

Страница 15: ...ry in stalled connection box prepared with wiring for positive and negative connections The cables are fitted with quick release connectors The electrical cables between the panels and the inverter mu...

Страница 16: ...he cable is se curely in place by carefully pulling it 6 3 4 Nm 6 Fasten the connector s sleeve so that the cable is se cure and so that the sleeve is at the bottom 3 4 Nm Caution Check that the polar...

Страница 17: ...er on the wall bracket according to the dia gram above The inverter must also be earthed as illustrated then cover the switch with silicone to protect against corro sion Switch 10 12mm 40 45mm L1 L2 L...

Страница 18: ...rews cable grommets that have not been tightened Set time and date Set Language 2 s 2000 00 00 00 00 2 s 1234567890 Normal 20 s Normal 2018 09 07 Error log Date Time Language Histogram SetTime 11 20 2...

Страница 19: ...For information regarding lightning protection see page 8 under Installation FUNCTIONS NIBE Uplink With NIBE Uplink and the Internet you can obtain a quick overview and the current status of the solar...

Страница 20: ...lass reverse and aluminium frame are undamaged Check that all electrical wiring and connections are intact and not coated with anything Mechanical cleaning is not usually required and is not recommend...

Страница 21: ...our 2 Number of trackers MPPT IP65 Enclosure class 40 32 20 16 16 16 A Rec fuse rating 057 204 057 230 057 203 057 202 057 201 057 200 Part No EME 20 included in inverter PVI 10 81x81x28 m m External...

Страница 22: ...1 1 Roof bracket sheet metal roof Part no 057 182 1 pcs PRM 41 1 Roof bracket felt roof Part no 057 183 1 pcs PRM 31 1 Roof bracket seamed sheet metal roof Part no 057 184 1 x PRM 51 1 Ceiling bracket...

Страница 23: ...nformation Recovery 5 Safety information 4 L Lightning protection potential compensation 8 M Marking 4 S Safety information 4 Marking 4 Symbols on PV Solar package 4 Safety instructions 8 Static load...

Страница 24: ......

Страница 25: ......

Страница 26: ......

Страница 27: ...nibe fi NORWAY NETHERLANDS GREAT BRITAIN ABK AS Brobekkveien 80 0582 Oslo Tel 47 23 17 05 20 post abkklima no nibe no NIBE Energietechniek B V Energieweg 31 4906 CG Oosterhout Tel 31 0 168 47 77 22 i...

Страница 28: ...y Systems All product illustrations facts and data are based on the available information at the time of the publication s approval NIBE Energy Systems makes reservations for any factual or printing e...

Отзывы: