Power Up and Initial Checkout
Connect the Backup Battery
Network Controller 6 Mounting and Wiring Guide
Part Number 11843 Rev 2.1
Updated: January 16, 2012
19
Power Up and Initial Checkout
Ensure power wiring to the T-600 controller is ready—see the
section on page 11. Refer to
on page 7 for the locations of the T-600 battery connector, status LEDs and barrel power connector (for
WPM-
XXX
on page 12 for location of the power connector on the
module.
Following all mounting and wiring, perform the following:
Procedure 7
Initial power up and checkout
Step 1
.
Step 2
.
Step 3
Connect the Backup Battery
With the cover removed from the T-600 (see
“Removing and Replacing the Cover,”
page 6), locate the red and
black wires coming from the NiMH backup battery, with 2-position connector plug. Insert the plug into the
battery connector on the base board (below option slot 2 area), as shown in
Figure 9
NiMH backup battery connector on T-600 controller base board.
The connector is keyed—you cannot insert it incorrectly. The red (positive) connection should be the furthest
from the two 30-pin option board connectors. For more battery details, see
Apply Power
Apply power to the T-600 by plugging in the power plug into either the T-600 (if wall mount AC adapter
) or the 24V-powered
module. If powering using the line-voltage input
power supply module, energize the 90–263 Vac circuit wired to the module.
Caution
Do not connect
both
the WPM-
XXX
and NPB-PWR / NPB-PWR-UN supplies at the same time, or
equipment damage may result, or a power outage may go unrecognized.
Battery
Assembly
Battery
Connector