FLOAT PANS
FLOAT PANS
FLOAT PANS
FLOAT PANS
“Panning” is the earliest step that can be performed on wet concrete. The optional float
pan allows the NXT-90 to begin working on concrete at the earliest possible time after the
pour, and is the most effective tool for floating the concrete. The float pan fits to the
existing finishing blades with minimal effort. As the concrete cures, panning will become
more taxing on the NXT-90. At this time, switch to using float blades or finish blades.
FIGURE 1
FIGURE 1
FIGURE 1
FIGURE 19
9
9
9:::: TYPICAL NXT-90 FLOAT PAN
Avoid lifting the NXT-90 with the float pan
installed. The pan may be secure enough
to slide the equipment or lift over minor
curbs, but it may fall if lifted so ALWAYS
avoid situations where it will cause injury