FERTIKIT 3G
INSTALLATION MANUAL
33
ON-SITE PREPARATIONS
Electrical preparation
Mains connection
CAUTION
Only qualified electricians are permitted to perform electrical installations!
The following components have to be provided in the installation:
•
A readily accessible circuit breaker, rated according to the FertiKit™'s total rated power certified as a
branch circuit over current protector (see
Appendix - Dosing booster electrical data
, page 46),
compliant with the national code and requirements.
•
Grounding connection: ≤ 10 Ω.
For the selection of the wire size - consider (see
Appendix - Dosing booster electrical data
, page 46):
•
The FertiKit™'s total rated power.
•
Whether the electricity supply is single-phase or three-phase.
(if a dosing booster is not present in the system, select the single-phase, up to 1.5 kWatt option).
Mains wire size for single-phase system
3 wires: GND, N, L
Power source required (kWatt) 1 X 100-115 VAC
1 X 200-250 VAC
Up to 1.5
≥ 2.5 mm
2
(≤ 13 awg)
≥ 2.5 mm
2
(≤ 13 awg)
1.5-2
≥ 4 mm
2
(≤ 11 awg)
2-3
≥ 6 mm
2
(≤ 9 awg)
Mains wire size for three-phase system
5 wires: GND, N, L1, L2, L3
Power source required (kWatt) 3 X 200-250 VAC
3 X 400-480 VAC
Up to 1.5
≥ 2.5 mm
2
(≤ 13 awg)
≥ 2.5 mm
2
(≤ 13 awg)
1.5-2
2-3
3-4
≥ 4 mm
2
(≤ 11 awg)
4-6
≥ 6 mm
2
(≤ 9 awg)
6-8
≥ 10 mm
2
(≤ 7 awg)
≥ 4 mm
2
(≤ 11 awg)