Overview of the Active Upgrade Process
1-8
Express5800/320
Fc
: Active Upgrade™ User’s Guide
Active Upgrade State Model
The state model in
Figure 1-6
shows all of the possible Active Upgrade states, and the
order in which they occur during the Active Upgrade process.
Figure 1-6. Active Upgrade State Model
The state model helps to demonstrate the sequence of events in the Active Upgrade
process, as follows:
1. All upgrade sessions start in the Idle state, where you can run the readiness check
as many times as necessary to verify that your system meets the prerequisites of
the upgrade process. The system continues to run normally, and both sides of the
system continue to be synchronized.
2. When you start an upgrade session, the Active Upgrade console switches to the
PrepareSplit state, during which it runs a final readiness check and additional
background tasks. If the system is ready, the console immediately switches to the
Split state and proceeds to divide the system into two independently running
systems.
Commit
Abort
Abort
Abort
Abort
Abort
Finish
Finish
Idle
Execute
Merge
Prepare
Merge
Execute
Split
Prepare
Split
Prepare
Split
Readiness
Split Mode
Merge
Prepare
Merge
Split
Commit
Finish
Idle
Check
duet005a
Содержание 320Fc
Страница 1: ...NEC Corporation of America 456 01720 000 Express5800 320Fc Active Upgrade User s Guide ...
Страница 8: ...Tables vi Express5800 320Fc Active Upgrade User s Guide ...
Страница 12: ...Preface x Express5800 320Fc Active Upgrade User s Guide ...
Страница 22: ...Overview of the Active Upgrade Process 1 10 Express5800 320Fc Active Upgrade User s Guide ...
Страница 98: ...Viewing Active Upgrade Process Status 4 28 Express5800 320Fc Active Upgrade User s Guide ...
Страница 120: ...Index Index 6 Express5800 320Fc Active Upgrade User s Guide ...