5.
In case vision is obstructed when handling the machine, recommended movement is to
reverse the forklift. There should be a coworker on the side to give instructions and en-
sure safety. The driving speed of the forklift should be as slow as possible.
3.2
Preparation before installation
10 days before installation, the site and handling path should be arranged. Meanwhile, to en-
sure machine precision and service life, make sure to consider the impact of environment on
the machine, and take appropriate measures to make improvement or prevention. In case it is
impossible to satisfy the following “installation space”, “installation foundation” and “envi-
ronmental requirements”, please adopt proper measures for improvement and contact our fac-
tory or dealer, so that technicians can handle the case instead. Do not attempt to handle the
case without knowing the circumstances, or it may result in damage to personnel or the ma-
chine.
3.2.1
Requirement of installation space
1.
The exterior dimensions of the machine may vary due to different equipment. For stand-
ard dimensions, refer to 2.6 of this manual.
2.
To avoid failure to install the machine because of insufficient space after the machine is
delivered to the place of installation. Make sure to measure the space where the machine
shall be installed and see if the space of handling path is satisfactory to standards 30 days
before the machine is scheduled to arrive at the place of installation. If not, make sure to
notify our factory or dealer as soon as possible. They shall try to provide recommenda-
tions and consultation service to settle any doubts concerning space requirements for ma-
chine installation.
3.2.2
Establishment of foundation
To maintain machine precision on a permanent basis, we suggest you make sound and proper
work for the foundation according to the standards for machine foundations. If foundation
work is not robust, it will cause the machine to vibrate and affect its precision and quality.
The machine foundation must be built 10 days before the machine is scheduled to arrive at the
place of installation, otherwise if the foundation is not yet set when the machine is delivered
to the place of installation, installation of the machine will be delayed. Working procedure as
follows:
1.
First, refer to the dimensions in the foundation drawing and excavate foundation chan-
nels, then pave its bottom layer with pebbles to solidify the foundation.
2.
Grout concrete, making sure spaces for foundation bolt channels are reserved according to
the foundation drawing.
3.
After the concrete is set, spread flat plates onto the reserved foundation bolt channels.