1. Completely tighten the flare nuts, A, B, C, D, connect 
    the manifold valve charge hose to a charge port of the 
    packed valve on the gas pipe side.
2. Connect the charge hose connection to the vacuum 
    pump.
3. Fully open the handle Lo of the manifold valve.
4. Operate the vacuum pump to evacuate. After starting 
    evacuation, slightly loose the flare nut of the packed 
    valve on the gas pipe side and check that the air is 
    entering. (Operation noise of  the vacuum pump changes 
    and a compound meter indicates 0 instead of minus)
5. After the evacuation is complete, fully close the handle 
    Lo of the manifold valve and stop the operation of the 
    vacuum pump.
    Make evacuation for 15 minutes and more and check 

5

    that the compound meter indicates  -76cmHg(-1.0x10 Pa).

O

6. Turn the stem of the packed valve B about 45  counter-
    clockwise for 6~7 seconds after the gas coming out, then 
    tighten the flare nut again. Make sure the pressure display 
    in the pressure indicator is a little higher than the atmosphere 
    pressure.
7. Remove the charge hose from the Low pressure charge hose.
8. Fully open the packed valve stems B and A.
9. Securely tighten the cap of the packed valve.

Manifold valve

Compound meter

-76cmHg

Handle Lo

Handle Hi

Charge hose

Charge hose

Vacuum pump

Pressure gauge

Packed valve

Perform  test operation after completing gas leak check at the flare nut connections and electrical 
safety check.
    Check that all tubing and wiring have been properly connected.
    Check that the gas and liquid side service valves are fully open.
1. Connect the power, press the ON/OFF button on the remote controller to turn the unit on.
2. Use the MODE button to select COOL, HEAT, AUTO and FAN to check if all the functions works 
     well. 

O

O

3.  When the ambient temperature is too low(lower than 17 C/62 F), the unit cannot be controlled by the 
     remote controller to run at cooling mode, manual operation can be taken. Manual operation is 
     used only when the remote controller is disable or maintenance necessary.
     Hold the panel sides and lift the panel up to an angle until it remains fixed with a clicking sound.
     Press the Manual control button to select the AUTO or COOL, the unit will operate under Forced 
     AUTO or COOL mode(see User Manual for details).
4.  The test operation should last about 30 minutes.

2. When using the Vacuum Pump

4. Test running

3. Safety and leakage check

A: Lo packed valve  B: Hi packed valve 
C and D are ends of indoor unit connection.

CAUTION

1. Soap water method:
     Apply a soap water or a liquid neutral detergent on the indoor 
     unit connections and outdoor unit connections by a soft brush 
     to check for leakage of the connecting points of the piping. If 
     bubbles come out, it indicates that the pipes have leakage.
2.  Leak detector
     Use the leak detector to check for leakage.

Indoor unit
check point

D

B

C

A

Outdoor unit
check point

Cover

AUTO/COOL

AUTO/COOL

Manual control button

9

Содержание NH23

Страница 1: ......

Страница 2: ...tion 4 Outdoor unit installation 7 1 INSTALLATIONPLATE MOUNTING DRILL A HOLEIN THE WALL CONNECT THE CABLE TO THE INDOORUNIT CONNECTIVE PIPE AND DRAINAGE INSTALLATION OUTDOOR INSALLATION PRECAUTION DRA...

Страница 3: ...or fixing is not perfect it will cause heat up or fire at the connection 6 Wiring routing must be properly arranged so that control board cover is fixed properly If control board cover is not fixed pe...

Страница 4: ...nce or other obstacles Do not place any obstacles which may cause a short circuit of the discharged air Anchor the outdoor unit with a bolt and nut 10 or 8 tightly and horizontally on a concrete or ri...

Страница 5: ...o the wall structure and corresponding mounting points on the installation plate The installation plate providedwith the machine differ from appliance to appliance Dimensions are in mm unless otherwis...

Страница 6: ...wrong figures 2 When connecting extension drain hose insulate the connecting part of extension drain hose with a shield pipe do not let the drain hose slack Drainage Right Wrong Suggest Minimum Wire S...

Страница 7: ...te until hooks engages with the their slots CAUTION Indoor unit installation 1 For the left hand and right hand piping remove the pipe cover from the side panel 2 For the right back and left back pipi...

Страница 8: ...rain joint then insert the drain joint into the base pan hole of outdoor unit rotate 90 to securely assemble them To install drain joint as shown in Fig B insert the drain joint into the base pan hole...

Страница 9: ...vacuum pump Additional amount of refrigerant to be charged Open the valve stem until it hits against the stopper Do not try to open it further Securely tighten the valve stem cap with a spanner or the...

Страница 10: ...the flare nut connections and electrical safety check Check that all tubing and wiring have been properly connected Check that the gas and liquid side service valves are fully open 1 Connect the powe...

Страница 11: ......

Страница 12: ...PLAQUE DE MONTAGE PERCEZ UN TROU DANS LE MUR CONNECTER LE C BLE SUR L UNITE EXTERIEURE INSTALLATION DU TUYAU DE RACCORDEMENT ET DE DRAINAGE 4 4 5 UNITE EXTERIEURE PRECAUTIONS D INSTALLATION A L EXTER...

Страница 13: ...lez dans un endroit solide qui pourra soutenir sans probl me le poids de l appareil Si le mur n est pas assez solide ou si l installation n est pas correctement r alis e l appareil pourra tomber et ca...

Страница 14: ...obstacles Ne placez pas d obstacles qui pourraient provoquer un court circuit de l air vacu 10 or ou 8 Ancrez l unit ext rieur avec un boulonet un crou de fermement et horizontalement sur une fixatio...

Страница 15: ...plaque de montage La plaque de montage fournie avec la machine peut varier les dimensions sont en mm moins que cela ne soit sp cifi autrement NOTE NOTE Fixation de la plaque de montage Le mur portant...

Страница 16: ...es 2 Lors de la connexion de l extens ion du tuyau de vidange isolez la partie de raccordement du tuyau de vidange avec un tuyau de protection et ne laissez pas pendre le tuyau de vidange Drainage Cor...

Страница 17: ...e comme indiqu Pour les mod les 9K 12K il n y a qu une seule conception de la structure de drainage de c t Pour le mod le 18k une structure de drainage lat ral est standard Un drainage des deux c t s...

Страница 18: ...re et faites letourner 90degr spourless curiserensemble Pourinstallerlejointdedrainagecommemontr surlaFigB ins rezlejoint dedrainagedansletrouaufonddur cipientdel unit ext rieure jusqu cequ il metteun...

Страница 19: ...serrage de la tige du bouchon de valve voir le tableau des couples de serrage Bouchon Capuchon Corps de la valve Tige de la valve Pour le mod le de r frig rant R410A assurez vous que le frigorig ne aj...

Страница 20: ...ct s V rifiez que les valves de service de gaz et de liquide soient bien ouvertes 1 Branchez appuyez sur le bouton MARCHE ARR T de la t l commande pour allumer l unit 2 Utilisez le bouton MODE pour s...

Страница 21: ...2020323B6002...

Отзывы: