10
Installation and operation manual
–
DTHR-V9-2020
Vertical discharge
Step 1:
•
Install the unit on an insulated floor
Step 2:
•
Install walls on each side (see dimension table);
•
The walls must be in contact with the guides on the
support structure;
•
The walls must be insulated with 2’’ of high temperature
insulation.
Step 3:
• Install the air baffle on the internal side of the roof;
•
Put the roof in place.
• The walls must be insulated with 2’’ of high temperature insulation.
Step 4:
• Seal and caulk with high
temperature sealant.