background image

20 of 10

Subject to change without prior notice

INSTALLATION OPERATION AND  MAINTENANCE INSTRUCTIONS

VERTICAL TURBINE PUMP - NVT SERIES

Ref. No. NVT-IOM/2020/V.01

6.2. Start up

Start the pump against a closed discharge valve only. Once the pump has reached full speed slowly open the valve 
and set to the duty point. Start up of the engine and controllers shall be as given in their respective IOM manuals. 
Automatic starting of the pumps shall be based on pressure setting.

6.3. Methods of Stopping

Manual:

Manual shut down shall be accomplished by operation of push-button on the outside of the controller enclosure.

Automatic shutdown after automatic start:

Automatic shutdown shall not be permitted where the pump constitutes the sole supply of fire sprinkler or standpipe 
system or where authority having jurisdiction has required normal shutdown.

Automatic shutdown shall be permitted only where the controller is arranged for automatic shutdown after all starting 
and returning causes have returned to normal.

7. MAINTENANCE

7.1. Weekly Inspection And Testing

The purpose of the weekly fire pump inspection and test is to ensure the fire pump is in an operation condition free of 
physical damage and is capable of providing continuous delivery for required fire protection demands. An additional 
purpose of the weekly test is to detect deficiencies that may not be obvious by visual inspection.

7.2. Visual Inspection

 

»

Check the power indicating light on the controller to verify that there is power to the pump

 

»

Make sure that the temperature in the pump room is not less than 

40

°F (

70

°F for diesel engines without 

heaters) during colder months.

 

»

Check ventilating louvers to make sure that they are free to operate.

 

»

Check pump discharge valves to make ensure that they are open.

 

»

Examine piping, fitting, and connections for any physical damage or leakage.

 

»

Check discharge gauge to make sure that the pressure reading is normal.

 

»

Check the system pressure gauge to ensure that the system pressure reading is normal. 

 

»

Make sure that the test header valves are closed in properly.

 

»

Check pressure sensing line leakage and block (open drain valve and check block).

 

»

Check free rotation of the pumps.

 

»

Check to make sure the phase reversal alarm pilot light is off.

Содержание NVT 6-115

Страница 1: ...INSTALLATION OPERATION MAINTENANCE NAFFCO FIRE PUMPS VERTICAL TURBINE PUMP NVT SERIES I N S T R U C T I O N S...

Страница 2: ...hile operating diesel engine Always wear safety shoes and safety gloves Monitor water leakage of pump gland packing If excessive leak adjust the packing do not place hands or finger into this area Dur...

Страница 3: ...ire pump set it should be very careful not to broke or bend it Column and shaft should be supported by suitably sized timbers while laying on floor Strainer if fitted on the pump should be removed pri...

Страница 4: ...TIONS VERTICAL TURBINE PUMP NVT SERIES Ref No NVT IOM 2020 V 01 5 INSTALLATION Fire water pump sets and control systems should be installed in accordance with this IOM maual Failure to install the sup...

Страница 5: ...anent and rigid support to the entire pump Foundation area should have adequate space for future inspection and maintenance activities and should be sufficient enough to provide a solid footing The fo...

Страница 6: ...ce it between the discharge head and the mounting flange align with the foundation bolts Continue to lower the pump assembly until the bolts enter the holes in the base Place wedges under the discharg...

Страница 7: ...hoist the driver up Inspect the mounting surface register and clean these surfaces thoroughly Any burrs found on the mounting surface should be removed using a smooth mill file and clean afterwards Po...

Страница 8: ...ons before proceeding further Install the top drive coupling or clutch over the top shaft Insert the ratchet pins In case of ball type ratchet place the ratchet balls and install the rotating half of...

Страница 9: ...sting on the lateral bowl wear rings and considerable resistance due to friction can be felt when turning the shaft by hand To set impellers to the mid position proceed as follows Turn the adjusting n...

Страница 10: ...on the base frame as shown in the Fig No 9 All shims must be perfectly flush and uniformly tighten up using securing means Base plates have to be grouted with non shrinking mortar up to the upper edge...

Страница 11: ...flange discharge head mounting flange and foundation If any leveling problem is found between discharge head mounting flange and foundation it can be corrected by shimming between them 3 Eccentricity...

Страница 12: ...e proceeding further with the installation Universal joint operating angles at each end of a drive shaft should always be at least 1 At the same time this deflection angles 1 and 2 must be equal withi...

Страница 13: ...RATION AND MAINTENANCE INSTRUCTIONS VERTICAL TURBINE PUMP NVT SERIES Ref No NVT IOM 2020 V 01 shown in the Fig No 14 in order for the angle 1 and 2 be equal when the angle is measured using the method...

Страница 14: ...NS VERTICAL TURBINE PUMP NVT SERIES Ref No NVT IOM 2020 V 01 Water tank should provide sufficient and reliable water supply for the fire protection system The depth of the tank should match with the p...

Страница 15: ...y requirements for piping and these must be strictly observed Refer to the appropriate standard for details See Fig No 19 The discharge piping should be supported independently and close to the pump s...

Страница 16: ...V 01 Install piping as straight as possible avoiding unnecessary bends Where necessary use 45 or long sweep 90 bends to decrease friction losses Make sure that all piping joints are airtight Where inc...

Страница 17: ...ion Yes No 15 Cooling system from heat exchanger or cooling water supply pipe line from pump discharge is installed Engine Yes No 16 Cooling line return line one size higher than inlet and this return...

Страница 18: ...shaft guard and pump stuffing box guard are fixed Yes No 6 OPERATION 6 1 Check List for Fire Pump Set Prior to Operation Commissioning SL NO DESCRIPTION RESULT 1 Check the foundation Yes No 2 Check t...

Страница 19: ...e the proper connection of discharge line Ensure all fasteners are tightened Yes No 15 Ensure that all joints and splines of drive shaft are lubricate before startup Yes No 16 Check the all the fasten...

Страница 20: ...CE 7 1 Weekly Inspection And Testing The purpose of the weekly fire pump inspection and test is to ensure the fire pump is in an operation condition free of physical damage and is capable of providing...

Страница 21: ...the pressure in the controller sensing line After starting the pump should be run at least 10 minutes Record the pressure at which the pump automatically started Record the pump suction and discharge...

Страница 22: ...ord current reading should be 2 to 5 amps after 5 minutes of running time Verify that engine will start off of both sets of batteries Verify operation of all supervisory signals i e pump running contr...

Страница 23: ...b Wrap packing around the shaft before cutting Fig No 20 9 Cut the coil on the marked point to form a gland packing ring It should be cut diagonally at an angle of 45 degree 10 Check the first ring to...

Страница 24: ...removing the bolts connecting them Remove the discharge head carefully without damaging or bending the shaft Disconnect the top column section by removing the bolts from the joint below it Carefully r...

Страница 25: ...side diameter slightly smaller than the outside diameter of the bearing Use bearing pullers to pull out the suction bell bearings 8 4 Inspection Replacement and Reassembly Inspect the pump parts after...

Страница 26: ...LLATION OPERATION AND MAINTENANCE INSTRUCTIONS VERTICAL TURBINE PUMP NVT SERIES Ref No NVT IOM 2020 V 01 8 5 Exploded View of Split case Fire Pump Fig No 22 1 2 3 5 4 6 7 8 9 10 11 12 13 14 20 21 23 2...

Страница 27: ...Lock Nut 14 NVT 13014 Upper Line Column Pipe 32 NVT 13032 Suction Bell 15 NVT 13015 Middle Line Shaft 33 NVT 13033 Sleeve for Suction Bell 16 NVT 13016 Bearing Retainer 34 NVT 13034 Suction Bearing 17...

Страница 28: ...liper Calibrated micrometer Spanner 1 set Multimeter Fiber Mallet Screw Driver Packing hook wire hook Pocket knife Machinist s level 9 3 Recommended Consumables Lubricating oil Grease Vaseline Sulfuri...

Страница 29: ...l voltage Speed is too low Check if driver is directly across the line and receiving full voltage Defective motor Consult factory Wrong rotation Ensure that pump is rotating CCW when viewed from above...

Страница 30: ...adding stages or increase impeller diameter Field head requirement greater than design head Check system friction loss increase discharge piping size Consult factory for adding stages or increase impe...

Страница 31: ...te the system Misalignment Realign pump and driver Motor or gear drive hollow shaft end play maladjustment Adjust the end play as given in the driver IOM manual Foreign object lodged between impeller...

Страница 32: ...C Electrical system 1 Exercise isolating switch and circuit breaker X Monthly 2 Trip circuit breaker if mechanism provided X Annually 3 Operate manual starting means electrical X Semiannually 4 Inspec...

Страница 33: ...ank level X X Weekly b Tank float switch X X Weekly c Solenoids valve operation X X Weekly d Strainer filter or dirt leg or combination thereof X Quarterly e Water and foreign material in tank X Annua...

Страница 34: ...l level X X Weekly b Oil change X 50 hours or annually c Oil filter s X 50 hours or annually d Lube oil heater X Weekly e Crankcase breather X X X Quarterly 3 Cooling system a Level X X Weekly b Antif...

Страница 35: ...r heater X Weekly i Inspect duct work clean louvers combustion air X X X Annually j Water strainer X Quarterly 4 Exhaust system a Leakage X X Weekly b Drain condensate trap X Weekly c Insulation and f...

Страница 36: ...ng voltage exceeds 9 volts on a 12 volt system or 18 volts on a 24 volt system X Weekly 6 Electrical system a General inspection X Weekly b Tighten control and power wiring connections X Annually c Wi...

Страница 37: ...r authorizes any other person to assume for it any other liability in connection with such equipment This warranty will be considered void by the following 1 Failure to provide regular maintenance in...

Страница 38: ...38 of 10 Subject to change without prior notice INSTALLATION OPERATION AND MAINTENANCE INSTRUCTIONS VERTICAL TURBINE PUMP NVT SERIES Ref No NVT IOM 2020 V 01 NOTES...

Страница 39: ...Project Name Location Commissioned By Date of Commissioning Signature of Commissioning Engineer...

Отзывы: