Pre-Energization Checks
15
Reference the image number callouts for additional verification locations:
1. Perform a gentle control wiring pull test of the AC control power terminations
2. Perform a gentle control wiring pull test of the sensor connectors from the Heyco’s
Control Panel Wiring Pull Test Locations
Once operational - please contact our development team to help make sure that all
software, monitoring, and data collection sections are prepared and ready to begin
active operation.
Содержание CommsSafe AC-1
Страница 3: ...Resources 2 Example myPV CommsSafe 2021 AC 1 Shown...
Страница 5: ...Resources 4 Back Panel for CommsSafe in Production Shown with Customer Supplied Equipment Added...
Страница 19: ...Initial Energization 18 24V DC 0 1V 23 9 24 1V voltage on the top input terminals of the UPS...
Страница 20: ...Initial Energization 19 24V DC 0 1V 6 0V 23 9 30 0V voltage on the top battery terminals of the UPS...
Страница 25: ...Troubleshooting 24 A fully seated fuse that is not blown in the AC block...